PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : OR-014/2014
1. Location of the project/Scheme : Orissa
 (i) State / Union Territory : Orissa  (ii) District : Sundargarh  (iii) Forest Division : Sundargarh  (iv) Area of forest land proposed for diversion (in ha.) : 39.98  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Sundargarh39.98Revenue Forest
Total 39.98
Division 1. : Sundargarh
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Sundargarh39.98
Total39.98
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
139.980.5Eco 3
Total. 39.98


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Acacia Ariciloformis0389928611485676989
Total 0 38992861 1485676 989
Sub Total (No of Trees.) 9910


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The Project is widening of existing 2 lane road to
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 1
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : The porject site dose not from part of any nationa
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.noDistrict NameVillageArea(in ha.)khasraKML filePresent Owner file
NO Data

Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Sundargarh357639171225.591150.528221042.4211/11/2014855.468109.727
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
SundargarhRourkelaDFOYesOne01/11/2014
 Nodal OfficerNoNo Data
 RourkelaCFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
SundargarhRourkelaDFO RecommendedIt is the expansion of the existing RoW of the nroad is approximately 10mt. it is no possiable to widen thw road widening the road with the existing RoW. Hence the project corridor requires forest/private land for road widenning adjacement to the road on both sides ofbthe road.. 1. The project would result in substantial finbancial and social benefits. 2. The Project will r5 esult in Substantial savings in terms of vehicle operating costs and travel costs. 3. The Project eill reduce existi
RourkelaCF RecommendedThe proposal is for the expansion of the existing RoW of the road approx 10mtrs. Hence the project corridor requires forest/ private land adjacent to the road on both sides. The project result in substantial savings in terms of vehicle operating and travel cost. The project will reduce the traffic congestion, accidents.
quetiapin ritalin quetiapin und valdoxan quetiapin wirkstoff
Yes
Nodal Officer RecommendedRecommended for diversion of 39.98 ha of forest land for widening of 2- Lane road to 4- Lane from Bankibahal to Kanika Railway siding under Sundargarh Forest Division
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
OrissaState SecretaryRecommended10/08/2015recommended vide letter no 14037 dated 06.08.2015.State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BhubaneswarRegional Office5-ORC259/2015-BHU14/10/2015
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/OR/ROAD/7575/2014ROAD7575201470513,578,500.0013,578,500.0012/10/2020SBINR52020101200103589Corporation BankNEFT/RTGS (Challan)01/10/202008/10/2020
FP/OR/ROAD/7575/2014ROAD7575201415317,727,500.0017,727,500.0004/03/2022SBIN306270364698Union Bank Of IndiaNEFT/RTGS (Challan)18/02/202223/02/2022
FP/OR/ROAD/7575/2014ROAD7575201408620,765,281.0020,765,281.0002/04/2022SBIN409176047135Union Bank Of IndiaNEFT/RTGS (Challan)31/03/202231/03/2022
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 41.921   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)41.921
  Status of CA Land so identified : Non Forest Area   Site Name : Village- Biswanathpur, under Hemgiri Tahasil, Sundargarh District.   Location Details : Village- Biswanathpur, Khata No-36/AJA, Plot No- 767, 768,769,770 & 773 under Hemgiri Tahasil, Sundargarh DIstrict.   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
RourkelaSundargarhHemgir4/201723 Sep 202041.921
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/OR/ROAD/7575/201416 Mar 2023No Dataverified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/OR/ROAD/7575/201406 Dec 2024
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/OR/ROAD/7575/201418 Aug 2023EDS: Please comply the EDS vide this office Memo No. 418 dated 06.01.202409 Jan 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/OR/ROAD/7575/2014The compliance to the conditions imposed by GoI MoEF & CC IRO Bhubaneswar as well as State Govt. is sent herewith vide this office letter No. 21049 dated 17.1.2022 for according final approval.21 Aug 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/OR/ROAD/7575/2014Approved In-PrincipleNo Data