PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
OR-08/2019
1.
Location of the project/Scheme :
Orissa
(i)
State / Union Territory :
Orissa
(ii)
District :
Sundargarh
(iii)
Forest Division :
Bonai
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.28
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Bonai
0.28
Revenue Forest
Total
0.28
Division 1. : Bonai
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Sundargarh
0.28
Total
0.28
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.28
0.2
Eco 1
Total.
0.28
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Shorea robusta
Sal
0
0
2
0
3
7
Total
0
0
2
0
3
7
Sub Total (No of Trees.)
12
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
The applied area is not vulnerable to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.5
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Wild animals such as Jungle cat, Mongooses, Rabit, Jackal etc. and different types of Snake and Birds are also seen in the applied area
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
Yes
(a)Details of violation(s):
The details of violation has been furnished at Par
(b) Period of Work done(year) :
2014
(c) Area of forest land involved in violation (in ha.) :
0.125
S. No.
Name of person responsible for violation
Designation & Address of person responsible for violation
Action taken against the person responsible for violation
1
Sri Basu Munda So Late Singhrai Munda Sri Singhrai Bhanwar So Indar Bhanwar
Local villagers
The Collector, Sundargarh has been requested to take legal action against the above persons for the encroachment vide this office Letter No.3195 dt.4.5.2019 for unauthorized occupation and construction of 2 houses over 0.031 ha. Besides, the Collector, Sundargarh has also been requested to take action for existence of path covering an area of 0.094 ha. of Revenue Forest land within the area applied for diversion located outside the Plant premises
12.
Whether work in violation is still in progres(Yes/No) :
Yes
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
NO Data
(ii).
Copy of CA scheme details:
NA
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority:
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Sundargarh
971200
495732
6014.002
53
8038.110
01/01/2019
8038.110
1122.460
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Bonai
Rourkela
DFO
Yes
One
15/04/2019
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Bonai
Rourkela
DFO
Recommended
In view of the above position, grant of approval for diversion of 0.28 ha. of forest land for construction of approach road from NH 520 to Kamanda Steel Plant of M/s Rungta Mines Ltd. under section 2 ii of the Forest Conservation Act’1980 may be considered.
Rourkela
CF
Recommended
As per diversion proposal, the approach road is is required for transportation of raw materials and finished goods
Yes
Nodal Officer
Recommended
Recommended for diversion of 0.28 ha of forest land for construction of approach road from NH 520 to Kamanda Steel Plant under Bonai Forest Division of Sundargarh district, Odisha by M/s Rungta Mines Ltd for approval under Section 2 of Forest Conservation Act,1980
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Orissa
State Secretary
Recommended
22/07/2019
recommended vide letter no 13738 dated 19.07.2019.
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Bhubaneswar
Regional Office
5-ORB389/2019-BHU
30/07/2019
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/OR/ROAD/35474/2018
ROAD354742018071
304,932.00
304,932.00
20/08/2019
BARBR52019082000818586
Corporation Bank
NEFT/RTGS (Challan)
16/08/2019
20/08/2019
FP/OR/ROAD/35474/2018
ROAD354742018687
422,800.00
422,800.00
17/09/2019
BARBR52019091700899929
Corporation Bank
NEFT/RTGS (Challan)
09/09/2019
16/09/2019
FP/OR/ROAD/35474/2018
ROAD354742018067
4,410.00
4,410.00
21/01/2020
BARBR20021335728
Corporation Bank
NEFT/RTGS (Challan)
13/01/2020
21/01/2020
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/OR/ROAD/35474/2018
01 Oct 2019
No Data
verified
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/OR/ROAD/35474/2018
20 Mar 2020
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/OR/ROAD/35474/2018
Compliance to the conditions imposed by Govt. of India, MoEF & CC, New Delhi is sent vide this office letter No.5827 dated 12.03.2020 for according final approval.
20 Mar 2020
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/OR/ROAD/35474/2018
23 Mar 2020
APPROVED