PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
OR-064/2016
1.
Location of the project/Scheme :
Orissa
(i)
State / Union Territory :
Orissa
(ii)
District :
Sundargarh,Jharsuguda
(iii)
Forest Division :
Sundargarh,Jharsuguda
 (iv)
Area of forest land proposed for diversion (in ha.) :
19.43
 (v)
Category of the Proposal:
Railway
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Sundargarh
19.32
Revenue Forest
2
Sundargarh
0.11
District Level Committee (D.L.C.) Forest
3
Jharsuguda
0
Civil Soyam land
Total
19.43
Division 1. : Jharsuguda
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Jharsuguda
0
Total
0
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0
0
Eco 6
Total.
0
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
NIL
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
NIL
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NIL
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
NIL
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
NIL
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
NIL
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
NIL
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
NIL
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
NIL
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
NIL
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
NO Data
Additional information Details
S. No.
Documents
Remarks
NIL
Division 2. : Sundargarh
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Sundargarh
19.43
Total
19.43
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
19.43
0.6
Eco 3
Total.
19.43
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
Not vunerable to soil erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.4
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
National Park, wild life sanctuary, biosphere reserve, tiger reserveare not coming under the Project. But, Occasional movement of elephant is noticed especially during paddy Harvesting season.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
34430880.00
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
NO Data
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Sundargarh
971200
171225
2511.3095
30
2031.83
31/10/2016
1198.740
252.358
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Sundargarh
Rourkela
DFO
Yes
One
26/03/2017
Jharsuguda
Sambalpur
DFO
Yes
One
22/05/2017
Sambalpur
CF
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Sundargarh
Rourkela
DFO
Recommended
During the site selection process care has been taken: I. To avoid forest land as far as possible. II. To avoid Non-Forest land having forest growth or higher vegetative density. III. To avoid displacement of population. But in order to maintain the continuity of the Railway Siding it is necessary to divert certain forest land which comes in the path. Out of the total land requirement of the project of 59.90 Ha, only 19.43 Ha of Forest land is proposed for diversion purpose which is the bare
quetiapin ritalin
markenavntablet.site
quetiapin wirkstoff
Jharsuguda
Sambalpur
DFO
Recommended
linear project
Sambalpur
CF
Recommended
Yes
Rourkela
CF
Recommended
As per the Project Proposal NTPC needs to connect with MCL Railway line for meeting the balance coal requirement at Kechobahal and Laikera end and also for transportation of oil rakes to the power plant.
Yes
Nodal Officer
Recommended
Recommended for diversion of 19.43 ha of forest land for construction of Railway Siding Corridor to connect NTPC MGR Line with MCL Railway Line at Laikera and Kechobahal ends for meeting the balance coal requirement and also for transportation of oil rakes to the Power Plant of NTPC Ltd. under Divisional Forest Officer, Sundargarh and Jharsuguda Forest Division by the Executive Director, NTPC Ltd., Darlipali STPP for approval under Section-2 (ii) of Forest (Conservation) Act, 1980.
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Orissa
State Secretary
Recommended
14/05/2018
Recommended vide letter no 11100 dated 14.05.2018.
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Bhubaneswar
Regional Office
5-ORC349/2018-BHU
18/06/2018
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/OR/RAIL/20055/2016
RAIL200552016804
31,683,290.00
31,683,290.00
10/07/2018
SBINR52018071000017283
Corporation Bank
NEFT/RTGS (Challan)
04/07/2018
06/07/2018
FP/OR/RAIL/20055/2016
RAIL200552016204
554,000.00
554,000.00
12/09/2018
SBINR52018091200022782
Corporation Bank
NEFT/RTGS (Challan)
03/09/2018
07/09/2018
FP/OR/RAIL/20055/2016
RAIL200552016424
6,937,700.00
6,937,700.00
28/06/2022
SBIN617891408399
Union Bank Of India
NEFT/RTGS (Challan)
02/06/2022
04/06/2022
FP/OR/RAIL/20055/2016
RAIL200552016421
8,269,214.00
8,269,214.00
04/09/2023
125596
Union Bank Of India
NEFT/RTGS (Challan)
24/08/2023
29/08/2023
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
38.86
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
38.86
Status of CA Land so identified :
Forest Area
Site Name :
Gundi Protected Reserve Forest
Location Details :
Kalahandi
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Gundi Protected Reserve Forest
PF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/OR/RAIL/20055/2016
25 Oct 2018
No Data
xvbvnbm,n
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/OR/RAIL/20055/2016
24 May 2024
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/OR/RAIL/20055/2016
The point wise compliance to the conditions imposed by GoI MoEF & CC IRO Bhubaneswar is sent herewith vide this office Letter No.456 dated 06.01.2024 for according final approval.
01 Jun 2024
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/OR/RAIL/20055/2016
26 Jun 2024
APPROVED
Print
Checklist for State Nodal Officer
×