PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : OR-031/2022
1. Location of the project/Scheme : Orissa
 (i) State / Union Territory : Orissa  (ii) District : Sundargarh  (iii) Forest Division : Rourkela  (iv) Area of forest land proposed for diversion (in ha.) : 0.7  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Rourkela0.7Reserved Forest
Total 0.7
Division 1. : Rourkela
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Sundargarh0.7
Total0.7
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.70.4Eco 3
Total. 0.7


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Tectona GrandisSaguan713344210
2Anogeissus acuminataPhasi001000
3Butea monospermaFalsha001001
4Pterospermum AcerifoliaKarmi000100
5ChirronjiChar010000
6OthersDoka010000
7OthersBaranda001000
8OthersAchu010000
Total 7 13647 31 1
Sub Total (No of Trees.) 195


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : This is a linear project, Hence vulnerability of forest area to erosion is in significant
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.5
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
NO Data
(ii). Copy of CA scheme details: NA (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.: (V). Copy of NOC from Competent Authority:
Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Sundargarh277700108389.77247.036417
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
RourkelaRourkelaDFOYesOne04/06/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
RourkelaRourkelaDFO RecommendedIn view of the above position, the proposal for diversion of 0.700 ha of Reserved forest land in Rourkela Forest Division for forest land for Proposed Water Conductor system from Mandira Dam to Power House Point of M/s GEDCOL Sail Power Corporation Limited near Laing village under Sundargarh District, is forwarded herewith in 5 sets along with its supporting documents for consideration on its own merit and onward transmission to Govt. of India for diversion in favour of M/s GEDCOL Sail Power Corporation Limited, Rourkela Steel Plant under Rourkela Forest Division in Sundargarh district of Odisha.
RourkelaCF RecommendedWater conductor systemYes
Nodal Officer RecommendedRecommended for diversion of 0.700 ha of Reserved Forest land for Water Conductor system from Mandira Dam to Power House Point of M/s GEDCOL SAIL Power Corporation Limited near laing village under Rourkela Forest Division of SUndargarh District, Odisha for approval under Section 2 ii of FC Act, 1980
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
OrissaState SecretaryRecommended09/09/2022RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BhubaneswarRegional Office5-ORB530/2022-BHU20/04/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/OR/Others/154167/2022OTHERS1541672022435860,013.00860,013.0002/09/2023123499Union Bank Of IndiaNEFT/RTGS (Challan)25/08/202329/08/2023
FP/OR/Others/154167/2022OTHERS15416720228202,872,070.002,872,070.0022/12/2023UBINJ23356142682Union Bank Of IndiaNEFT/RTGS (Challan)18/12/202321/12/2023
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/OR/Others/154167/202221 Mar 2024No Dataverified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/OR/Others/154167/202225 Mar 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/OR/Others/154167/2022The compliance to the conditions imposed by GoI MoEF & CC IRO Bhubaneswar as well as State Govt. is sent herewith vide this office letter No.16552 dated 24.08.2022 for according final approval.09 Apr 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/OR/Others/154167/202224 Apr 2024APPROVED