PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MP-084/2016
1.
Location of the project/Scheme :
Madhya Pradesh
(i)
State / Union Territory :
Madhya Pradesh
(ii)
District :
Khargaone,Barwani
(iii)
Forest Division :
Barwah(T),Sendhwa(T)
 (iv)
Area of forest land proposed for diversion (in ha.) :
39.437
 (v)
Category of the Proposal:
Transmission Line
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Barwah(T)
11.866
Reserved Forest
2
Sendhwa(T)
27.571
Reserved Forest
Total
39.437
Division 1. : Barwah(T)
3.
District wise area to be diverted in the division
S. No.
District
Area(in ha.)
NIL
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
11.866
0.2
Eco 5
Total.
11.866
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Tectona Grandis
Sagwan
0
51
0
0
0
0
2
Others
Mixed Species
0
301
9
2
1
1
Total
0
352
9
2
1
1
Sub Total (No of Trees.)
365
5.
Working plan prescription for the forest land proposed for diversion :
Soil and Water conservation working Circle
6.
Brief note on vulnerability of the forest area to erosion :
NA
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Not any Specific Flora & Fauna found in the proposed area.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
134.93761
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
24
RF
Balawada
RF139
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
DFO Inspection Report
2
District Collector Certificate 196 dated 11.01.2017 for FRA 2006
Division 2. : Sendhwa(T)
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Barwani
27.571
Total
27.571
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
27.571
0.4
Eco 3
Total.
27.571
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Tectona Grandis
Sagon
0
77
9
0
0
0
2
Others
Mix
0
202
79
24
7
5
Total
0
279
88
24
7
5
Sub Total (No of Trees.)
403
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
NA
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Details attached
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
29596675
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
55.5
RF 95
Balawada
95
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Wild life report sendhwa
2
Minimum forest land sendhwa
3
DFO Sendhwa site inspection report
4
FRA Barwani for sendhwa
5
Certified copy of PART-II
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Barwani
544200
228625
351.299
13
119.320
21/06/2017
126.293
12.683
2
Khargaone
10334.440
2687.82
2627.085
42
5
31/03/2017
323.368
17.84
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Barwah(T)
Khandwa(T)
DFO
Yes
One
14/04/2017
Sendhwa(T)
Khandwa(T)
DFO
Yes
One
06/06/2017
Khandwa(T)
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Barwah(T)
Khandwa(T)
DFO
Recommended
This project will be used for Pwer Transmission to BDTCL Dhule Substation from NTPC TPP 1320 MW at Selda under Khargone District. It will form an integral part of Western Region System Strengthening. Since the proposed Transmission Line bare minimum forest land. The Route alignment of the Proposed line affects minimum trees. There will be generation of employment during the project Execution & Maintenance. So, the project is being forwarded with Recommendation for further process.
Sendhwa(T)
Khandwa(T)
DFO
Recommended
This project will be used for power transmission to BDTCL Dhule substation from NTPC TPP 1320 MW at Selda under Khargone District. It will become an integral part of Western Region System Strengthening. The proposed transmission line is affecting bare minimum forest land and minimum trees. There will be employment generation during the execution, operation & maintenance of project. The project for diversion of 27.571 Hectare is being forwarded with recommendation for further process.
Khandwa(T)
CF
Recommended
The Project for diversion of 39.437 Ha. forest land is being forwarded with recommendation for further process
Yes
Nodal Officer
Recommended
Construction of 765 KV DC Hexa Khandwa - Dhule Transmission Line (39.437 ha. forest land) is recommended in favour of Project Head, Khargone Transmission Ltd. Sanavad (M.P.)
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Madhya Pradesh
State Secretary
Recommended
26/08/2017
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Bhopal
Regional Office
6-MPC031/2017-BHO
07/11/2017
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MP/TRANS/22331/2016
TRANS223312016023
66,321,850.00
66,321,850.00
21/02/2018
10465
Corporation Bank
NEFT/RTGS (Challan)
09/02/2018
12/02/2018
FP/MP/TRANS/22331/2016
TRANS223312016023
66,321,850.00
66,321,850.00
21/02/2018
ICICR52018022100823494
Corporation Bank
NEFT/RTGS (Challan)
NA
NA
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/MP/TRANS/22331/2016
25 Feb 2018
No Data
.
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/MP/TRANS/22331/2016
25 Feb 2018
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/MP/TRANS/22331/2016
27 Feb 2018
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MP/TRANS/22331/2016
05 Jun 2020
APPROVED
Print