PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MP-0118/2021
1. Location of the project/Scheme : Madhya Pradesh
 (i) State / Union Territory : Madhya Pradesh  (ii) District : Khandwa,Burhanpur  (iii) Forest Division : Khandwa(T),Burhanpur(T)  (iv) Area of forest land proposed for diversion (in ha.) : 21.49  (v)

Category of the Proposal: Railway
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Khandwa(T)6.18Reserved Forest
2Burhanpur(T)15.31Reserved Forest
Total 21.49
Division 1. : Burhanpur(T)
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Burhanpur15.31
Total15.31
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
115.310.5Eco 3
Total. 15.31


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Teaksagoan346146212735009317
2Misc. Speciesother4451031756359133109
Total 791 24932029 859226 126
Sub Total (No of Trees.) 6524


5. Working plan prescription for the forest land proposed for diversion : the compartment are in IWC Working circle 289, 290& FV 294
6. Brief note on vulnerability of the forest area to erosion : Not Vulnerable
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 00
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : 1. Barking deer - Muntjac 2. Canis aureus - Jackal 3. Hyaena hyaena - Hyaena 4. Macaca mulata - Monkey 5. Sus-scrofa - wild boar 6. Vulpes bengalensis - Fox 7. Blue Bull - Boselaphus Tragocamelus, 8. Panthor (Leopard) - Panthera Pardus
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 250.85
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1143RFAsir158    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 minimum land utilization letter
2 tree goshwara letter
3 NO Violation letter
4 CA Scheme
5 FRA -2006 LETTER
6 joint survey report letter
Division 2. : Khandwa(T)
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Khandwa6.18
Total6.18
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
16.180.5Eco 3
Total. 6.18


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Tectona GrandisTeak 4191313148211
2Misc. SpeciesOther12331263993218
Total 16 522576 24753 19
Sub Total (No of Trees.) 1433


5. Working plan prescription for the forest land proposed for diversion : Compartment No. 748 SCI working Circle
6. Brief note on vulnerability of the forest area to erosion : No
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Blue Bull, Monkey, Wild Pig etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
NO Data

Additional information Details
S. No. DocumentsRemarks
1 Certificate
2 Site Inspection Report
3 Tree Goshwara
4 Letter

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Burhanpur342700190102460.139220012/01/202215.3100
2Khandwa759308283723.8738995.3349915.4730/06/2021745.6449.91
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Khandwa(T)Khandwa(T)DFOYesOne04/09/2021
Burhanpur(T)Khandwa(T)DFOYesOne12/01/2022
 Khandwa(T)CFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Khandwa(T)Khandwa(T)DFO RecommendedRecommeded
Burhanpur(T)Khandwa(T)DFO RecommendedIt is recommended to divert 15.31 ha. Of forest land to user agency deputy chief engineer south central railway Akola Maharashtra for proposed construction proposed Gauge Conversation of existing Railway Track from Meter Guage to Broad Guage between Khandwa Amlakhurd Station.
Khandwa(T)CF RecommendedLetter No. DM/2022/50 dated 17 01 2022Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Madhya PradeshState SecretaryRecommended02/03/2022.State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BhopalRegional Office6-MPC066/2021-BHO09/05/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MP/RAIL/140205/2021RAIL140205202144241,552,211.0041,552,211.0024/05/2022SBIN522144396075Union Bank Of IndiaNEFT/RTGS (Challan)15/05/202215/05/2022
FP/MP/RAIL/140205/2021RAIL14020520214707,655,435.007,655,435.0029/06/2022655325Union Bank Of IndiaNEFT/RTGS (Challan)22/06/202222/06/2022
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/MP/RAIL/140205/202107 Jul 2022No DataVerify
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/MP/RAIL/140205/202107 Jul 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/MP/RAIL/140205/2021.07 Jul 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MP/RAIL/140205/202103 Oct 2022APPROVED