PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MP-051/2016
1.
Location of the project/Scheme :
Madhya Pradesh
(i)
State / Union Territory :
Madhya Pradesh
(ii)
District :
Singrouli
(iii)
Forest Division :
Singrauli
 (iv)
Area of forest land proposed for diversion (in ha.) :
467.809
 (v)
Category of the Proposal:
Mining
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Singrauli
443
Protected Forest
Total
443
Division 1. : Singrauli
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Singrouli
467.809
Total
467.809
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
187
0.2
Eco 5
2
256
0.4
Eco 5
Total.
443
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Madhuca indica
Mahua
0
5900
1630
570
250
660
2
Shorea Robusta
Saal
0
20200
9170
1880
380
170
3
Lagerstroemia Parviflora
Sendha
0
4270
1170
160
50
10
4
Diasporus Melanoxylon
Tendu
0
15670
3440
480
100
60
5
Ficus Bengalensis
Bargad
0
0
0
0
10
10
6
Terminialia Crenulata
Saaja
0
5540
560
120
10
0
7
Dalburgia Sisoo
Shisoo
0
10
0
0
0
0
8
Syzigium Cumini
Jamti
0
390
100
30
20
20
9
Azadirachta Indica
Neem
0
160
110
10
0
0
10
Schleichera oleosa
Kusum
0
70
0
0
0
10
11
Bombax Ceiba
Semar
0
30
0
0
0
0
12
Terminalia Chebula
Harra
0
110
0
0
10
0
13
Boswellia Serrata
Salaya
0
30
30
20
0
0
14
Buchanania lanzan
Achar
0
6720
1520
250
90
50
15
Lannea coromandelica
Gunja
0
6620
1200
100
0
20
16
Others
0
19580
2280
480
120
40
Total
0
85300
21210
4100
1040
1050
Sub Total (No of Trees.)
112700
5.
Working plan prescription for the forest land proposed for diversion :
RDF
6.
Brief note on vulnerability of the forest area to erosion :
Normal
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
No
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
Yes
Details and comments on the impact of Project on such areas :
In the working plan of Singrauli division compartment No. 262 is included in Elephant corridor.
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
4541.65
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
4
25.00
PF
Jiyavan
PF 746
View file
2
5
20.00
RF
Karthua
RF 17
View file
3
6
20.00
RF
Karthua
RF 848
View file
4
7
20.00
RF
Karthua
RF 772
View file
5
8
50.00
PF
West Sarai
PF 606
View file
6
9
25.00
PF
West Sarai
PF 612
View file
7
24
50.00
RF
Mada
RF 424
View file
8
21
50.00
RF
Waidhan
RF 399
View file
9
1
25.00
RF
Jiyavan
R 813
View file
10
2
25.00
PF
Jiyavan
PF 777
View file
11
3
25.00
PF
Jiyavan
PF 763
View file
12
16
100.00
RF
Bargawan
RF 578
View file
13
17
50.00
PF
Chitrangi
PF 01
View file
14
18
50.00
PF
Chitrangi
PF 81
View file
15
19
50.00
PF
Chitrangi
PF 75
View file
16
22
40.00
PF
Waidhan
PF 287
View file
17
23
36.00
RF
Waidhan
RF 402
View file
18
10
25.00
PF
West Sarai
PF 669
View file
19
11
50.00
PF
Gorbi
PF 158
View file
20
12
50.00
PF
Gorbi
PF 182
View file
21
13
50.00
PF
Gorbi
PF 187
View file
22
14
50.00
PF
Gorbi
PF 178
View file
23
15
50.00
RF
Bargawan
RF 246
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Singrouli
567282.244
221656.88
6790.691
37
8512.592
31/12/2015
6339.042
2418.421
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Singrauli
Rewa(T)
DFO
Yes
One
19/08/2016
Rewa(T)
CF
No
No Data
Rewa(T)
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Singrauli
Rewa(T)
DFO
Recommended
Rewa(T)
CF
Not-Recommended
Proposal un completed send to dfo singorli
No
Nodal Officer
Recommended
Recommended.
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Madhya Pradesh
State Secretary
Recommended
31/10/2017
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Bhopal
Head Office
8-57/2017-FC
19/04/2018
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MP/MIN/13685/2015
MIN136852015610
867,173,966.00
867,173,966.00
27/06/2018
UBINR52018062700031522
Corporation Bank
NEFT/RTGS (Challan)
21/06/2018
21/06/2018
FP/MP/MIN/13685/2015
MIN136852015139
213,400,000.00
213,400,000.00
23/12/2020
SBIN235703364518
Corporation Bank
NEFT/RTGS (Challan)
21/12/2020
21/12/2020
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/MP/MIN/13685/2015
15 Nov 2019
No Data
agree
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/MP/MIN/13685/2015
15 Nov 2019
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/MP/MIN/13685/2015
15 Nov 2019
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MP/MIN/13685/2015
03 May 2021
APPROVED
Print
Checklist for State Nodal Officer
×