PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MP-015/2017
1. Location of the project/Scheme : Madhya Pradesh
 (i) State / Union Territory : Madhya Pradesh  (ii) District : Dhar  (iii) Forest Division : Dhar(T)  (iv) Area of forest land proposed for diversion (in ha.) : 119.25  (v)

Category of the Proposal: Irrigation
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Dhar(T)119.25Reserved Forest
Total 119.25
Division 1. : Dhar(T)
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Dhar119.25
Total119.25
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
1119.250.3Eco 3
Total. 119.25


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Tectona Grandissagoun0102876554118
2Boswellia Serratasalar003622
3Lannea coromandelicaMoyan01119442
4Anogeissus latifoliaDhawada0252000
5Azadirachta IndicaNeem0105510
6Terminalia BellaricaBaheda025232
7Dalbergia paniculataFasi (pathrali)034000
8Morinda tinctoriaAal066371782
9Wrigtria TingtoriaDudhi0182210
10Delonix RegiaGulmohar 0121001
11Butea MonospermaPalas05023942
12Diasporus MelanoxylonTendu (Temroo)0188300
13embelica officinalisAnwala011247
14Ficus Lacorpipar001121
15Cassia Siameakaptiya001113
16Bombox CeibaSemal052321
17Hardwickia BinnataAnjan012100
18Pongamia PinnataKaranj031010
19Aegle MarmelosBilla (Bel)002000
20Kydia calycinaDhaman001000
21Tamarindus IndicaImli000010
22Albezzia AmaraKastar02834231614
23Sterculia urensKullu 011000
Total 0 1282920 13361 45
Sub Total (No of Trees.) 2441

(iii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-2 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

(iv) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-4 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Tectona GrandisSagoun06976754688
2Boswellia SerrataSalar003622
3Lannea coromandelicaMoyan01119442
4Anogeissus latifoliaDhawada0241000
5Azadirachta IndicaNeem0105510
6Terminalia BellaricaBaheda025232
7Dalbergia paniculataFasi (pathrali)034000
8Morinda tinctoriaAal061281572
9Wrigtria TingtoriaDudhi0161100
10Butea MonospermaPalas03820532
11Delonix RegiaGulmohar090001
12Diasporus MelanoxylonTendu (Temroo)074200
13embelica officinalisAnwala011247
14Ficus LacorPipar001121
15Cassia SiameaKaptiya001113
16Bombax CeibaSemal052321
17Hardwickia BinnataAnjan012100
18Pongamia PinnataKaranj031010
19Aegle MarmelosBilla (Bel)002000
20Kydia calycinaDhaman001000
21Tamarindus IndicaImli000010
22Albezzia AmaraKastar02130191614
23Sterculia urensKullu011000
Total 0 910807 11355 45
Sub Total (No of Trees.) 1930

5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : Forest area vulnderability to soil erosion in case
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Hyena -2, Wild Dog -12, Barking Deer -6, Jacal -7, Fox - 7, Here - 10
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1DharSalwa79.6119,26,27,28,29,30,31,32,33,37,38,46,51,65,66,8,13,76,77,78,79
2DharKhakriya Ghat39.6434,41,76
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 Layout plan
2 C A Project not upload Part II
3 C A Project not upload Part III
4 C A Project not upload Part IV
5 Recommendation of DFO.
6 FRL -2 Mt entry not allow

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Dhar815300130034813.580222395.71728/02/20172342.7149.721
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Dhar(T)Indore(T)DFOYesOne15/03/2017
 Indore(T)CFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Dhar(T)Indore(T)DFO RecommendedThe project will provide irrigation to 22 villages which will solve their water demand. This project has minimum forest area from technical purpose.
Indore(T)CF RecommendedJustification given by DFO is correctYes
Nodal Officer RecommendedConstruction of Karam Medium Tank (119.25 ha. forest land) is recommended for use of Water Resource Department.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Madhya PradeshState SecretaryRecommended27/04/2017 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BhopalHead Office8-36/2017-FC27/09/2017
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MP/IRRIG/20856/2016IRRIG208562016463144,656,000.00144,656,000.0008/11/2017105234Corporation BankCorporation Bank (Challan)13/10/201713/10/2017
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 119.25   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 2
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)79.61
  Status of CA Land so identified : Non Forest Area   Site Name : Karam Medium Tank   Location Details : Village-Salwa   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
Indore(T)Dhar(T)Sardarpur192/15-16/A-19(3)07 Sep 201679.61
  No. of patches : 2
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
2Block(Polygon)39.64
  Status of CA Land so identified : Non Forest Area   Site Name : Karam Medium Tank   Location Details : Village-Khakhriyaghat   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
Indore(T)Dhar(T)Sardarpur192/15-16/A-19(3)07 Sep 201639.64
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/MP/IRRIG/20856/201601 Dec 2017No DataAgreed
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/MP/IRRIG/20856/201603 Dec 2017
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/MP/IRRIG/20856/201619 Dec 2017
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MP/IRRIG/20856/201605 Apr 2018APPROVED