State Serial No. of proposal : ML-014/2020
1. Location of the project/Scheme : Meghalaya
 (i) State / Union Territory : Meghalaya  (ii) District : South Garo Hills  (iii) Forest Division : Garo Hills  (iv) Area of forest land proposed for diversion (in ha.) : 0.1  (v)

Category of the Proposal: Irrigation
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Garo Hills0.1Reserved Forest
Total 0.1
Division 1. : Garo Hills
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1South Garo Hills0.1
Total0.1
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.170Eco 1
Total. 0.1


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

(iii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-2 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

(iv) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-4 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

5. Working plan prescription for the forest land proposed for diversion : As per working plan prescription it falls under the Plantation WC, Forest Protection WC,JFMC WC, NTFP WC & Wildlife management WC.
6. Brief note on vulnerability of the forest area to erosion : The vulnerability of forest area to soil erosion remains minimum because for many years, the land remains the same and affect of erosion is not seen much.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.567
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Wildlife presence is not seen in these places, but in surrounding areas sometimes wild elephants passed through.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 4.64688
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.2AngratoliAngratoli (Independent Beat) 1    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1South Garo Hills185000010010008.2524411.252404/09/20210.10
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Garo HillsGaro HillsDFOYesOne26/07/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Garo HillsGaro HillsDFO RecommendedAs the Water Resources Department wanted to construct small irrigation dam project across the small stream, it may benefit the farmers especially for paddy cultivation. The villagers can also take up vegetable cultivation once this irrigation project is implemented, however during the lean period, the level of water may not be sufficient as this small stream reduce the flow from November to April. However, villagers will be benefitted especially during the paddy cultivation season.
Garo HillsCF Recommended The Water Resources Department, Baghmara took initiative for construction of irrigation dam across the small stream inside the Reserve Forest near Dumnikura sub beat to store water and use it for irrigating the paddy cultivation. The submergence area is only 0.10 hectares of Angratoli Reserve Forest land and no felling of trees is involved. This project will supply water to about 28.00 hectares of cultivable area and will be benefited to 37 thirty seven families of Telekali village. Thus this project will not only enhance the annual income of 37 families but also improve the quality of life of population, enhance ground water recharge, provide water source for aquatic life for flora and fauna.Yes
Nodal Officer RecommendedThe proposal pertains to diversion of 0.1 ha. of Angratoli Reserve Forest land for construction of Telekali Flow Irrigation Project by Water Resources Department, Baghmara. The purpose of the project by the Water Resources Department, Baghmara inside Angratoli Reserve Forest is to supply water to the paddy field to uplift the economic condition of the farmers of Telekali Village. The area of forest land being diverted is only 0.10 hectares with no felling of trees involved. The construction of irrigation will augment the water availability to both the agriculture fields and forest land. Hence, the proposal is recommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MeghalayaState SecretaryRecommended21/02/2023since the project is of public utility General approval conveyed State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ShillongState GovernmentFOR 53/202115/07/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/ML/IRRIG/44898/2020IRRIG448982020116373,063.00373,063.002022-04-27392133Union Bank Of IndiaUnion Bank Of India (Challan)2022-03-112022-03-13
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/ML/IRRIG/44898/2020IN-PRINCIPLENo Data