PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : ML-01/2020
1. Location of the project/Scheme : Meghalaya
 (i) State / Union Territory : Meghalaya  (ii) District : East Garo Hills  (iii) Forest Division : Garo Hills  (iv) Area of forest land proposed for diversion (in ha.) : 0.01  (v)

Category of the Proposal: Irrigation
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Garo Hills0.01Reserved Forest
Total 0.01
Division 1. : Garo Hills
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1East Garo Hills0.01
Total0.01
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.0140Eco 1
Total. 0.01


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

(iii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-2 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

(iv) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-4 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

5. Working plan prescription for the forest land proposed for diversion : The proposed forest land falls under the Plantation, Forest Protection, Joint Forest Management, Non-Timber Forest Produce and Wildlife Management Working Circle.
6. Brief note on vulnerability of the forest area to erosion : The Forest Land Proposed for Diversion is prone to erosion during the Floods, since it is situated within 50 m from the River bank of R.Manda
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.05
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Asian Elephant, Wild Boar, Common Fox, Common Mongoose, Monitor Lizard, Malayan Giant Squirrel etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : The Area proposed for Diversion of this Project falls under the Chimabangshi Reserve Forest, which is the Elephant Crossing Zone. Whereas, since the area proposed for the Project is only 0.01 Ha , there is no significant impact on the Elephant Crossing Zone.
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 0.35707
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.1Chimabangshi Reserve Forest Dainadubi 5    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 District Chosen as East Garo Hills, Due to Non Availability of North Garo Hills Option

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1East Garo Hills111300645152031/03/202000
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Garo HillsGaro HillsDFOYesOne06/03/2020
 Garo HillsCFYesOne27/07/2020
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Garo HillsGaro HillsDFO RecommendedThe proposed Hydrological Observation Station is under the National Hydrology Project, Government of India, and the data collected from the observation station will be used for water resources planning and for flood prediction and it is proposed in the above mentioned location in order to get the accurate details regarding the water flow and other parameters of the Manda River and its proximity to the Permanent Bridge. Also, since the area being diverted is only 0.01 Ha, with no felling of trees involved and since it is not an industry or an activity which causes pollution in any form. Thus, the proposed Hydrological Observation Station near the Manda River inside Chimabangshi Reserve Forest is Recommended.
Garo HillsCF RecommendedThe proposed Hydrological Observation Station is under the National Hydrology Project, Government of India, and the data collected from the observation station will be used for water resources planning and for flood prediction and it is proposed in the above mentioned location in order to get the accurate details regarding the water flow and other parameters of the Manda River. Also, since the area being diverted is only 0.01 Ha, with no felling of trees involved. Thus, the proposed Hydrological Observation Station near the Manda River inside Chimabangshi Reserve Forest is recommended.Yes
Nodal Officer RecommendedThe proposal pertains to construction of the Hydrological Observatory Station near Manda River at Satmile in the Chimabangshi Reserve Forest under Dainadubi Range of East and North Garo Hills Territorial Division. It is a project under National Hydrology Project, Govt. of India and the data collected from the observation station will be used for water resources planning and for flood prediction .Also the area being diverted is only 0.01Ha, with no tree felling. I therefore, concur to the views of Divisional Forests Officer T and Conservator of Forests T for diversion of the forest land for the aforementioned purpose.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MeghalayaState SecretaryRecommended17/01/2022since the project is meant for public purpose, Final approval granted under General approval category. State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ShillongState GovernmentFOR.50/2020/9313/01/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/ML/IRRIG/41289/2019IRRIG412892019400133,176.00133,176.0002/09/2021MEGBH21245356288Union Bank Of IndiaNEFT/RTGS (Challan)12/08/202113/08/2021
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/ML/IRRIG/41289/2019IN-PRINCIPLENo Data