PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MH-029/2015
1. Location of the project/Scheme : Maharashtra
 (i) State / Union Territory : Maharashtra  (ii) District : Nagpur  (iii) Forest Division : Nagpur  (iv) Area of forest land proposed for diversion (in ha.) : 1.705  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Nagpur1.705Zudpi jungle
Total 1.705
Division 1. : Nagpur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Nagpur1.705
Total1.705
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
11.7050.1Eco 3
Total. 1.705


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Acacia leucophloeaHiwar0202000
2Butea MonospermaPalas080000
3Anona SquamosaSitaphal060000
4Azadirachta IndicaNeem0190000
5Acacia NiloticaBabool001000
6OthersFatra010000
7Terminalia bellericaBeheda020000
8Mangifera IndicaAam000010
9Acacia CatechuKhair010000
10Diasporus MelanoxylonTendu033000
11OthersNewarkha075200
12OthersTiwas023100
13OthersKatsawar001110
14OthersRohan000010
15OthersChar010000
Total 0 7015 43 0
Sub Total (No of Trees.) 92


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The forest land involved in the project is prone to normal rates of erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : The proposed project area site is itself in the fo
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Not noticed.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 847567
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
113.416PFNorth UmredComptt. No. 382 (PF)    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 C A Land Geo map
2 Suitability cert CA 400KV Mauda_Baitul
3 CA Scheme
4 topo sheet C A Land

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Nagpur993100146079.514268.9879520.957524/09/2015520.95752742.74
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
NagpurNagpurDFOYesOne26/08/2015
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
NagpurNagpurDFO Recommended
NagpurCF RecommendedYes
Nodal Officer Recommended
quetiapin ritalin markenavntablet.site quetiapin wirkstoff
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MaharashtraState SecretaryRecommended04/12/2015 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
NagpurRegional OfficeFC-I/MH-16/2015-NGP12/05/2016
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MH/TRANS/8466/2014TRANS846620148414,482,312.004,482,312.0028/07/2016S23163578Union Bank Of IndiaNEFT/RTGS (Challan)21/06/201622/06/2016
FP/MH/TRANS/8466/2014TRANS846620148414,482,312.004,482,312.0028/07/2016S23163578Union Bank Of IndiaNEFT/RTGS (Challan)NANA
FP/MH/TRANS/8466/2014TRANS8466201460199,000.0099,000.0011/01/2017S28656533Union Bank Of IndiaNEFT/RTGS (Challan)06/01/201707/01/2017
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MH/TRANS/8466/2014Approved In-PrincipleNo Data