PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MH-0153/2020
1.
Location of the project/Scheme :
Maharashtra
(i)
State / Union Territory :
Maharashtra
(ii)
District :
Nanded
(iii)
Forest Division :
Nanded
 (iv)
Area of forest land proposed for diversion (in ha.) :
5.34
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Nanded
5.34
Reserved Forest
Total
5.34
Division 1. : Nanded
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Nanded
5.34
Total
5.34
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
5.34
0.2
Eco 3
Total.
5.34
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Butea Monosperma
Palas
3
52
19
1
0
0
2
Azadirachta Indica
Limb
0
1
2
2
0
0
3
Madhuca indica
Moha
0
4
2
2
1
0
4
Terminalia Bellarica
Behada
0
0
1
1
0
0
5
Others
Rohani
0
0
1
0
0
0
6
Others
Pimpari
0
0
0
1
0
0
7
Ailanthus excelsa
Maharukh
0
0
2
1
0
0
8
Cassia Fistula
Bahawa
0
3
0
0
0
0
9
Terminalia Tomentosa
Ain
0
7
5
2
0
0
10
Acacia leucophloea
Hiwar
0
1
0
0
0
0
11
Albezzia Labbeck
Shiras
0
0
0
0
0
1
12
Others
Charoli
0
2
0
0
0
0
13
Diasporus Melanoxylon
Tendu
1
0
0
0
0
0
14
Others
Dhawada
0
1
4
1
0
0
15
Ficus Religiosa
Pimpal
0
0
0
1
0
0
16
Semecarpus Anacardium
Biba
1
1
0
0
0
0
17
Lagerstroemia Parviflora
Lendi
0
1
0
0
0
0
18
Ficus Racemosa
Umbar
0
1
0
0
0
0
19
Wrigtria Tingtoria
Dudhi
1
1
0
0
0
0
20
Tectona Grandis
Sag
13
101
18
6
0
0
21
Others
Ragatbed
0
1
0
0
0
0
22
Others
Hanmanka
0
1
0
0
0
0
23
Others
Bhoi
2
0
0
0
0
0
Total
21
178
54
18
1
1
Sub Total (No of Trees.)
273
5.
Working plan prescription for the forest land proposed for diversion :
IWC
6.
Brief note on vulnerability of the forest area to erosion :
to some extent vulnerable for erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
peacock, wild pig & black buck etc
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
Yes
(a)Details of violation(s):
subgrade
(b) Period of Work done(year) :
2020
(c) Area of forest land involved in violation (in ha.) :
0.735
S. No.
Name of person responsible for violation
Designation & Address of person responsible for violation
Action taken against the person responsible for violation
1
Shakeel Tahasildar
project manager Nikhil Construction Pune
Notice issued to responsible officer regardingviolation of FCA act
2
D D Kolekar
Resident Engineer c v Kand Consultant Pvt Ltd pune JV with Shrikhande Consultant Pvt Ltd Mumbai
Notice issued to responsible officer regardingviolation of FCA act
12.
Whether work in violation is still in progres(Yes/No) :
No
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
72.15
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
10.68
RF
Nanded
401 B 403 A
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Part II online & offline uploaded
2
Site Inspection Report upload
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Nanded
1052000
130003.450
121.63
12
161.18
31/01/2021
161.18
2292.40
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Nodal Officer
No
No Data
Nanded
Aurangabad
DFO
Yes
One
13/02/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Nanded
Aurangabad
DFO
Recommended
The diversion of minimum forest land is recommended for the following reasons 1. Road proposed has been declared as National Highway connecting Nanded District of Maharashtra & Telangana state to create good connectivity between these two states. 2. This is being widening of existing road having 5.50 to 7.50 meter carriage width. Minimum forest is required which is unavoidable & no realignment is proposed in forest area. 3. Widening of road will improve socio economic status of Nanded & Bhokar tq. 4. Most of the areas are along the project Road is agriculture belt. And thus it also will boost up agriculture growth in this area.
Aurangabad
CF
Recommended
The forest land proposed to be diverted for this project is unavoidable and is the barest minimum.
Yes
Nodal Officer
Recommended
The diversion of minimum forest land is recommended for the following reasons No suitable alternate land is available and the forest land required is minimum. Proposed project is not likely to affect any mounmental site of cultural, historical, religious, archeological or recreational importance.
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Maharashtra
State Secretary
Recommended
07/12/2021
PCCF HoFF Office has recommended proposal for approval
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Nagpur
Regional Office
FC-II/MH-164/2021-NGP
31/12/2021
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MH/ROAD/47068/2020
ROAD470682020412
20,970,150.00
20,970,150.00
20/04/2023
928983
Union Bank Of India
NEFT/RTGS (Challan)
03/04/2023
05/04/2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MH/ROAD/47068/2020
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×