PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MH-081/2019
1. Location of the project/Scheme : Maharashtra
 (i) State / Union Territory : Maharashtra  (ii) District : Raigad  (iii) Forest Division : Alibag  (iv) Area of forest land proposed for diversion (in ha.) : 12.8957  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Alibag3.9249Finally acquired Private Forest
2Alibag4.9501Private Forest
3Alibag4.0207Reserved Forest
Total 12.8957
Division 1. : Alibag
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Raigad12.8957
Total12.8957
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
112.89570.2Eco 1
Total. 12.8957


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Misc. SpeciesTeak, Savar, khair, Ain, Hed, Shivan, Dhaman, Umber, etc1815513974810
Total 18 155139 7481 0
Sub Total (No of Trees.) 467


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The project area in not Vulnerable to erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : Yes
  (a)Details of violation(s): unauthorized construction of road
   (b) Period of Work done(year) : 2019.2020
   (c) Area of forest land involved in violation (in ha.) : 2.235
S. No. Name of person responsible for violation Designation & Address of person responsible for violationAction taken against the person responsible for violation
1messers Dev Ysh Brij GopalDirectorOffence was booked and offender is being prosecuted as per law
12. Whether work in violation is still in progres(Yes/No) : No
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 272.10139
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1126Protected ForestVihigaonNew 83 (old 341)    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Absence of alternative alingment
2 cronological events
3 Distance from protected area
4 Identified certificate
5 Identified forest list
6 Net present value certificate
7 Tree felling estimate and list of trees
8 violation report
9 wildlife certificate
10 Achiological certificate
11 Document verification
12 Information furnish in english
13 Violation certificate
14 Tree felling certificate

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Raigad7152001647681230.2019912113.095431/03/20202113.0954367.4640
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
AlibagThaneDFOYesOne22/06/2020
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
AlibagThaneDFO RecommendedThis proposal is for widening for road for augmentation of capacity for safe and efficient movement of traffic by upgrading to Two Lane with paved shoulder configuration based on the traffic demand. This will reduce time and cost of travel for public. Moreover only 12.8957 Ha. Forest area is diverted with no significant impact on existing flora and fauna so this proposal is recommended for acceptance and necessary approval in favour of the user agency. This project is recommended as this is an infrastructure development and public utility project. Project proponent is ready to bear all the Government levies hence the proposal is being recommended for approval for diverting the required forest land under Forest Conservation Act, 1980.
ThaneCF RecommendedThis Project is for widening of Road for augmentation of capacity for safe and efficient movement of Traffic by upgrading to Two lanes with paved shoulder configuration based on Traffic demand. Recommended as per recommendations of DYCF Alibag.Yes
Nodal Officer RecommendedThis Project is for widening of Road for augmentation of capacity for safe and efficient movement of Traffic by upgrading to Two lanes with paved shoulder configuration based on Traffic demand. Recommended as per recommendations of DYCF Alibag.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MaharashtraState SecretaryRecommended10/03/2021 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
NagpurRegional OfficeFC-II/MH-152/2021-NGP26/08/2021
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MH/ROAD/40239/2019ROAD40239201994647,910,013.0047,910,013.0007/12/2021CNRB234072951296Union Bank Of IndiaNEFT/RTGS (Challan)01/12/202102/12/2021
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/MH/ROAD/40239/201904 May 2022No DataCA proposed on Degraded Forest Land.
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/MH/ROAD/40239/201930 Apr 2025EDS: To upload physical copy. 02 May 2025
FP/MH/ROAD/40239/201928 Feb 2023EDS: For query compliance03 May 2023
FP/MH/ROAD/40239/201925 May 2023EDS: Query raised by this office letter Dated -07/08/202307 Aug 2023
FP/MH/ROAD/40239/201912 May 2022EDS: Query raised by this office letter dt 11-07-2212 Jul 2022
FP/MH/ROAD/40239/201903 Aug 2022EDS: Query Raised by this Office Letter Dated -18/10/202218 Oct 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/MH/ROAD/40239/2019Recommended03 Jun 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MH/ROAD/40239/2019Approved In-PrincipleNo Data