PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MH-0101/2018
1.
Location of the project/Scheme :
Maharashtra
(i)
State / Union Territory :
Maharashtra
(ii)
District :
Dhule,Jalgaon
(iii)
Forest Division :
Dhule,Jalgaon
 (iv)
Area of forest land proposed for diversion (in ha.) :
7.65
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Dhule
7.65
Reserved Forest
2
Jalgaon
0
Reserved Forest
Total
7.65
Division 1. : Dhule
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Dhule
7.65
Total
7.65
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
7.65
0.4
Eco 4
Total.
7.65
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Acacia Nilotica
Babhul
0
40
25
6
2
0
2
Hardwickia Binnata
Anjan
0
4
0
0
0
0
3
Acacia Catechu
Khair
11
152
34
2
0
0
4
Azadirachta Indica
Neem
6
49
41
35
9
5
5
Butea Monosperma
Palas
1
5
0
2
0
0
6
Leucosceptrum Canum Sm.
Subabul
1
17
21
15
4
0
7
Moringa oleifera
Shevga
0
2
3
0
1
0
8
Bauhinia Parviflora
Apta
0
35
4
0
0
0
9
Ailanthus excelsa
Maharukh
1
3
2
0
0
0
10
Gmelina Arborea
Shivan
5
20
1
0
0
0
11
Zizyphus Xylopyrus
Bor
14
147
15
3
1
0
12
Zizyphus Jujuba
Ghatbor
1
2
0
0
0
0
13
Acacia leucophloea
Hivar
9
245
70
6
0
0
14
Delonix Regia
Gulmohar
0
2
1
4
0
0
15
Santalum Album
Chandan
1
2
0
0
0
0
16
Prosophis Spicigera
Prosophis
8
106
35
12
1
0
17
Others
Chinchola
0
0
1
0
0
0
18
Others
Dhavda
2
12
1
1
0
0
19
Others
Dudhkudi
0
5
2
1
0
0
20
Others
Glyrisodia
5
9
0
0
0
0
21
Others
Hekal
3
12
1
0
0
0
22
Others
Hinganbet
1
15
1
1
0
0
23
Others
Kansar
0
1
2
0
0
0
24
Others
Kashid
1
14
12
0
0
0
25
Others
Lokhandi
4
33
9
4
0
0
26
Others
Modshim
0
4
3
0
0
0
27
Others
Murmakha
0
1
0
0
0
0
28
Others
Nilgiri
0
4
2
0
0
0
29
Others
Papda
0
1
2
0
0
0
30
Others
Probabul
1
5
0
1
0
0
31
Others
Ramkathibabul
0
0
1
0
0
0
32
Others
Sisam
1
8
5
2
2
2
33
Others
Vedibabl
0
2
0
0
0
0
34
Others
Yebabul
1
24
7
5
1
0
35
Others
Yelatur
5
22
1
0
0
0
Total
82
1003
302
100
21
7
Sub Total (No of Trees.)
1515
5.
Working plan prescription for the forest land proposed for diversion :
nil
6.
Brief note on vulnerability of the forest area to erosion :
The area consists of grey basaltic rock having medium grained texture. It is hard and compact. The proposed area is undulating. The area is not prone to severe erosion.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Canis aureus / herpestes edwaardsi / Gazella
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
8169732
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
15.30
RF
Dhule
327
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
Division 2. : Jalgaon
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Jalgaon
0
Total
0
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0
0
Eco 4
Total.
0
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
NA
6.
Brief note on vulnerability of the forest area to erosion :
NIL
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NIL
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
0
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.00
RF
Jalgaon
0
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Dhule
8228.00
1917.6317
1382.678
59
907.957
07/12/2018
907.957
465.03
2
Jalgaon
0
0
0
0
0
13/12/2018
0
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Dhule
Dhule
DFO
Yes
One
17/08/2018
Jalgaon
Dhule
DFO
No
No Data
Dhule
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Dhule
Dhule
DFO
Recommended
N.A.
Jalgaon
Dhule
DFO
Recommended
THERE IS NO FOREST LAND REQUIRED TO BE DIVERTED IN JALGAON FOREST DIVISION FOR THE PROJECT OF 4 LANING OF BODHARE TO DHULE SECTION OF NH211 IN THE STATE OF MAHARASHTRA IN PROPOSAL OF DIVERSION OF 7.65 HA FOREST LAND IN DHULE FOREST DIVISION. HENCE PROPOSAL IS RECOMMENDED FOR FURTHER APPROVAL.
Dhule
CF
Recommended
NA
Yes
Nodal Officer
Recommended
The N.H. authority of India has been entrusted for development maintenance and management of the highways by the Govt. of India under NHDP phase III programme. In this project, over all road safety situation will be improved and there will be decrease in road traffic accident immediately after implementation of the project. Summarily, up gradation of the project rod will have following benefits. 1 To accelerate regional economic development in terms of industry, tourism and agriculture. 2 To reduce vehicle operating and maintenance costs by improving road conditions. 3 To reduce travel time by minimizing congestion in urban streatches and providing a four lane facility over there etc
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Maharashtra
State Secretary
Recommended
18/12/2018
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Nagpur
Regional Office
FC-II-MH-98-2018-NGP
05/02/2019
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MH/ROAD/34842/2018
ROAD348422018252
15,781,428.00
15,781,428.00
16/02/2019
SYNBR92019021600236978
Corporation Bank
NEFT/RTGS (Challan)
15/02/2019
15/02/2019
FP/MH/ROAD/34842/2018
ROAD348422018844
5,313,000.00
5,313,000.00
18/08/2020
P20081808120171
Corporation Bank
NEFT/RTGS (Challan)
22/07/2020
22/07/2020
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/MH/ROAD/34842/2018
26 Nov 2021
No Data
Verify
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/MH/ROAD/34842/2018
26 Nov 2021
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/MH/ROAD/34842/2018
29 Nov 2021
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MH/ROAD/34842/2018
28 Feb 2021
APPROVED
Print