PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MH-0240/2021
1.
Location of the project/Scheme :
Maharashtra
(i)
State / Union Territory :
Maharashtra
(ii)
District :
Thane
(iii)
Forest Division :
Thane
 (iv)
Area of forest land proposed for diversion (in ha.) :
14.613
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Thane
5.672
Reserved Forest
2
Thane
2.493
Private Forest
3
Thane
6.448
Protected Forest
Total
14.613
Division 1. : Thane
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Thane
14.613
Total
14.613
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
14.613
0.2
Eco 1
Total.
14.613
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Acacia Catechu
Khauir
1
2
0
0
0
0
2
Terminalia Tomentosa
Ain
0
0
0
0
0
0
3
Tectona Grandis
Sag
2
1
0
0
0
0
4
Others
Others
31
48
25
10
12
0
Total
34
51
25
10
12
0
Sub Total (No of Trees.)
132
5.
Working plan prescription for the forest land proposed for diversion :
Yes
6.
Brief note on vulnerability of the forest area to erosion :
The Area is not vulnerable to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Rabit, Sneak, Dear,
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
Yes
(a)Details of violation(s):
Construction of Existing Vadape to Thane Road
(b) Period of Work done(year) :
1980
(c) Area of forest land involved in violation (in ha.) :
4.947
S. No.
Name of person responsible for violation
Designation & Address of person responsible for violation
Action taken against the person responsible for violation
1
V D BORKAR
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
2
U S KALGUTKAR
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
3
V D BORKAR
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
4
A T LONDHE
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
5
Y G PATWARDHAN
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
6
A T LONDHE
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
7
Y G PATWARDHAN
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
8
M R ASHTAVADHAN
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
9
B G CHIKHLIKAR
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
10
A K DESHAPANDE
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
11
M P DEVRE
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
12
H B KURIYA
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
13
H B KURIYA
EXEUTIVE ENGINEER NATIONAL HIGHWSY DIVISION THANE
Requested Secretary PWD Mantralaya Mumbai to take appropriate action against these officers as per MCSR for said violation of provisions of forest conservation act
12.
Whether work in violation is still in progres(Yes/No) :
Yes
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
20800668.28
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
30
Reserved Forest
Vaijapur
-
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Site Inspection Report
2
Suitability Certificate
3
CA Scheme
4
Part II
5
DCF Certificate
6
B Form
7
UA Certificate
8
voilatioin Report
9
Area Statement
10
Joint Inspectiion Report
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Thane
320693
77203.032
1389.211
102
1403.15
31/03/2021
1423.149
118.382
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Thane
Thane
DFO
Yes
One
07/12/2021
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Thane
Thane
DFO
Recommended
The Project undertaken by government of India NHAI is part of public infrastructure facility and essential for convenient, fast and safe travel. Though the project involves violation but over the period of time this road has developed as the main connecting link of Mumbai to other regions of the state. Hence this public infrastructure is of utmost need and the forest land involved is unavoidable due to the existing alignment of the road over non forest land. Hence, the proposal is recommended for acceptance after due consideration of violation happened over the period of time and charging of Penal NPV. The NPV rate to be charged for the forest land is to be at the rate of Eco Class I. The Project Authority should bear the necessary amount for construction of Chainlink Fencing Length 7980 Mtr., Forester Quarter Type II – 1 Nos., Forest Guard Quarter Type I – 1 Nos., Watch Tower 2 Nos.,Patrolling Vehicle – 2 Nos., Forest Check Post – 1 Nos. and CCTV System for effective protection of balance forest area along with Proposed National Highways. Details of above Conditional work attached in Annexure I The proposal is being recommended for acceptance.
Thane
CF
Recommended
Proposal Recommended for necessary action and approval
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Maharashtra
State Secretary
Recommended
11/05/2022
Recommended for approval subject to fulfillment of conditions and mitigation measures suggested in the proposal
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Nagpur
Regional Office
FC-II/MH-181/2022-NGP
21/06/2022
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MH/ROAD/148827/2021
ROAD1488272021377
67,274,405.00
67,274,405.00
04/08/2022
684735
Union Bank Of India
NEFT/RTGS (Challan)
02/08/2022
02/08/2022
FP/MH/ROAD/148827/2021
ROAD1488272021130
982,500.00
982,500.00
24/08/2022
700828
Union Bank Of India
NEFT/RTGS (Challan)
24/08/2022
24/08/2022
FP/MH/ROAD/148827/2021
ROAD1488272021973
93,645,033.00
93,645,000.00
04/06/2024
CNRBR52024060481794748
Union Bank Of India
NEFT/RTGS (Challan)
25/05/2024
27/05/2024
FP/MH/ROAD/148827/2021
ROAD1488272021571
8,743,975.00
8,743,980.00
Union Bank Of India
NEFT/RTGS (Challan)
19/11/2024
28/11/2024
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
30
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
30
Status of CA Land so identified :
Forest Area
Site Name :
Village Parala
Location Details :
Gut No. 352, 358, 359, 376
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Reserved Forest
RF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/MH/ROAD/148827/2021
20 Jun 2023
No Data
Verified
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/MH/ROAD/148827/2021
31 Jul 2024
Compliance Details Submitted by User Agency(old)
Proposal No.
Compliance Details submitted on(Date)
Reject Remarks
Reject Date
Uploaded Letter
FP/MH/ROAD/148827/2021
20 Jun 2023
EDS: Query raised by this office letter Dated -19/10/2023
19 Oct 2023
FP/MH/ROAD/148827/2021
19 Nov 2023
EDS: For Physical copy submission
28 Nov 2023
FP/MH/ROAD/148827/2021
03 Jun 2024
EDS: For Physical copy submission
30 Jul 2024
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/MH/ROAD/148827/2021
Recommended
04 Sep 2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MH/ROAD/148827/2021
03 Sep 2024
APPROVED
Print
Checklist for State Nodal Officer
×