PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MH-0212/2019
1. Location of the project/Scheme : Maharashtra
 (i) State / Union Territory : Maharashtra  (ii) District : Raigad  (iii) Forest Division : Alibag  (iv) Area of forest land proposed for diversion (in ha.) : 9.1321  (v)

Category of the Proposal: Railway
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Alibag4.8162Reserved Forest
2Alibag4.3159Private Forest
Total 9.1321
Division 1. : Alibag
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Raigad9.1321
Total9.1321
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
19.13210.1Eco 1
Total. 9.1321


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Tectona GrandisTeak7284000
2Misc. SpeciesSavar, Palas, Umber Dhavda, Dhaman ain, Vela, Sitafhal, Kaju rain tree, Karanj Fhans14256300
3Bambusa BambooBamboo52000000
Total 541 5310 30 0
Sub Total (No of Trees.) 607


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The project area is not vulnerable to erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : NIL
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 66.12730
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1120Reserved ForestSudhagad647    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 alternative examined for leaner project certificate
2 Archeological certificate
3 Area Statement
4 Identified forest
5 alternative alignment certificate
6 cost benefit analysis certificate
7 Distance of project area from protected Area
8 Document Verification Certificate
9 Wildlife certificate
10 No violation Certificate
11 NPV Certificate
12 Tree Felling certificate

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Raigad715200164768 1222.4483 892113.0954 31/03/20182066.0954 367.4640
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
AlibagThaneDFOYesOne24/12/2019
 ThaneCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
AlibagThaneDFO RecommendedThe proposal is recommended as it is infrastructure development project and proposal of national interest undertaken by Govt. of India. Project proponent is ready to bear all the Government levies hence the proposal is being recommended for approval for diverting the required forest land under Forest Conservation Act, 1980.
ThaneCF Recommendedccf covering letter and part 3 attachYes
Nodal Officer Recommendedrecommendation and Part IV n V
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MaharashtraState SecretaryRecommended10/03/2021 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
NagpurRegional OfficeFC-II/MH-156/2021-NGP30/05/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MH/RAIL/43265/2019RAIL43265201905527,105,870.0027,105,870.0015/07/2022669015Union Bank Of IndiaNEFT/RTGS (Challan)12/07/202213/07/2022
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/MH/RAIL/43265/201925 Jul 2022No Dataverified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/MH/RAIL/43265/201919 Jun 2025
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/MH/RAIL/43265/201904 Apr 2025EDS: To upload physical copy 02 May 2025
FP/MH/RAIL/43265/201922 Jun 2023EDS: First hard copy should be submitted in this office then proposal should be sent to Parivesh05 Jul 2023
FP/MH/RAIL/43265/201927 May 2025EDS: Query raised vide this office letter dt 05-06-202509 Jun 2025
FP/MH/RAIL/43265/201908 Jun 2023EDS: Query Raised by this office letter Dated -20/06/202320 Jun 2023
FP/MH/RAIL/43265/201910 Nov 2023EDS: For Hard copy submission20 Nov 2023
FP/MH/RAIL/43265/201925 Jul 2022EDS: For query compliance22 Sep 2022
FP/MH/RAIL/43265/201915 Dec 2022EDS: For query compliance28 Dec 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/MH/RAIL/43265/2019Recommended03 Aug 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MH/RAIL/43265/2019Approved In-PrincipleNo Data