PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MH-0168/2017
1. Location of the project/Scheme : Maharashtra
 (i) State / Union Territory : Maharashtra  (ii) District : Mumbai (Suburban)  (iii) Forest Division : Mangrove  (iv) Area of forest land proposed for diversion (in ha.) : 3.3  (v)

Category of the Proposal: Railway
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Mangrove0.321Private Forest
2Mangrove2.9534Forest by dictionary meaning
Total 3.2744
Division 1. : Mangrove
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Mumbai (Suburban)3.2744
Total3.2744
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
13.27440.6Eco 2
Total. 3.2744


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersTiwar221272196
Total 2 2127 219 6
Sub Total (No of Trees.) 86


5. Working plan prescription for the forest land proposed for diversion : NA
6. Brief note on vulnerability of the forest area to erosion : The project is the marshy land and too small in a size hence there is no vulnerability to forest land from erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : The distance from Sanjay Gandhi National Park is 4.3 km and distance from Thane Creek Flamingo Sanctuary is 16.1 km.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
113.2744othersWest MumbaiNA    View file

Additional information Details
S. No. DocumentsRemarks
1 DFO certificate
2 joint inspection report
3 part 2

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Mumbai (Suburban)9553004086891389.211961403.1531/03/20131423.149118.382
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
MangroveMangroveDFOYesOne13/10/2017
 MangroveCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
MangroveMangroveDFO RecommendedThe proposed project is for public utility project and it is useful and beneficial for society.
MangroveCF RecommendedThe Project is public utility project and it is useful and beneficial for society.Yes
Nodal Officer RecommendedMumbai Metropolitan Region is one of the fast growing metropolitan regions in India. In this public transport systems are overcrowded and the road network is congested as there is a large gap between the demand and supply. Currently major challenges is to provide connectivity and promote growth by providing additional infrastructure which would improve the quality of life of the residents. This project is a public utility project and it is useful and beneficial for society hence it is recommended.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MaharashtraState SecretaryRecommended11/01/2019 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
NagpurRegional OfficeFC-I-MH-138-2019-NGP14/02/2019
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MH/RAIL/28822/2017RAIL2882220173537,081,198.007,081,198.0014/05/2019MAHBH19134619342Corporation BankNEFT/RTGS (Challan)02/05/201910/05/2019
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MH/RAIL/28822/2017Approved In-PrincipleNo Data