PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MH-0174/2021
1. Location of the project/Scheme : Maharashtra
 (i) State / Union Territory : Maharashtra  (ii) District : Mumbai (Suburban),Thane,palghar  (iii) Forest Division : Mangrove,Dahanu  (iv) Area of forest land proposed for diversion (in ha.) : 12.7808  (v)

Category of the Proposal: Railway
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Dahanu7.6655Un-notified Mangrove Forest
2Mangrove5.1153Un-Notified (Railway Land)
Total 12.7808
Division 1. : Dahanu
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1palghar7.6655
2Thane1.4274
3Mumbai (Suburban)3.6879
Total12.7808
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
17.66550.6Eco 2
Total. 7.6655


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersMangrove (Avicennia Marina)11747736111
Total 117 47736 11 1
Sub Total (No of Trees.) 633


5. Working plan prescription for the forest land proposed for diversion : Nil
6. Brief note on vulnerability of the forest area to erosion : Minimum
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : NO
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
NO Data

Additional information Details
S. No. DocumentsRemarks
1
Division 2. : Mangrove
3. District wise area to be diverted in the division
S. No. DistrictArea(in ha.)
NIL
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
15.11530.6Eco 2
Total. 5.1153


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersMangrove1011065624177120
Total 101 1065624 17712 0
Sub Total (No of Trees.) 1979


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The area is not Vulnerable and there is no possibility of erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No, Distance from Sanjay Gandhi National Park is 1.8 km and Distance from Thane Creek Flamingo Sanctuary is 16.3 Km
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 161.49591
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1130RFPorla10    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Certificate of wildlife
2 Document verification certificate
3 no violation certificate
4 minimum demand certificate
5 tree cutting and felling certificate
6 Certificate of archaeological importance
7 npv certificate
8 joint inspection report

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Thane4214003450.18528.245313731/03/202270
2palghar5944002306241318.176151910.510031/03/2022910.5100164.1200
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
DahanuThaneDFOYesOne27/07/2022
MangroveMangroveDFOYesOne17/03/2022
 MangroveCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
DahanuThaneDFO RecommendedThe Project is undertaken by government of India MRVC is part of public infrastructure facility and essential for convenient, fast and safe travel. Hence this public infrastructure is of utmost need and the Un notified mangrove land involved is unavoidable due to the existing alignment of the railway line over non forest land. Hence, the proposal is recommended for acceptance. The NPV rate to be charged for the Un notified mangrove land is to be at the rate of Eco Class I. The Project Authority should bear the necessary amount for survey and demarcation, Artificial Bird nests, Watch Tower 1 Nos., Two storied Forest Check Post –1 Nos. and CCTV System for effective protection of balance forest area along with Proposed Mumbai Rail Vikas Corporation project. No construction debris/remains should be dumped in mangrove area. Once the construction is over the RoW should be restored with mangroves. The proposal is being recommended for acceptance.
MangroveMangroveDFO RecommendedMumbai Rail Vikas Corporation has proposed the construction of 5th and 6th line between Borivali to Virar with intension of increasing frequency of trains, reduction in travel time and also reduction in overcrowding in local trains. Hence the project is recommended as it is a public utility project
ThaneCF RecommendedProposal is recommended and forwarded for acceptance.Yes
MangroveCF RecommendedThe proposed project for construction of 5th and 6th line between Borivali to Virar with intension of increasing frequency of local trains reduction in travel time and also reduction in overcrowding in local trains. Hence the project is recommended as it is a public utility projectYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MaharashtraState SecretaryRecommended05/04/2023FLD 2023/CR84/F 10, Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
NagpurRegional OfficeFC-II/MH-212/2023-NGP17/11/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MH/RAIL/145390/2021RAIL145390202137143,334,861.0043,334,900.0005/12/2023RTGSIDFBR52023120500431862Union Bank Of IndiaNEFT/RTGS (Challan)NANA
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 30   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)30
  Status of CA Land so identified : Forest Area   Site Name : Village Deloda Range Porla Division Wadsa   Location Details : NIL   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Reserved ForestRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/MH/RAIL/145390/202118 Jan 2024No Dataverified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/MH/RAIL/145390/202118 Jan 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/MH/RAIL/145390/2021Recommended18 Jan 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MH/RAIL/145390/202122 Jan 2024APPROVED