PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MH-070/2019
1.
Location of the project/Scheme :
Maharashtra
(i)
State / Union Territory :
Maharashtra
(ii)
District :
Mumbai (Suburban),Raigad
(iii)
Forest Division :
Mangrove,Alibag
 (iv)
Area of forest land proposed for diversion (in ha.) :
22.9648
 (v)
Category of the Proposal:
Pipeline
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Alibag
12.0432
Mangrove Forest
2
Alibag
1.1712
Unclassed Forests
3
Alibag
0.3041
Private Forest
4
Alibag
0.6784
Reserved Forest
5
Alibag
0.9667
Proposed Reserved Forests (Sec-4 of IFA)
6
Mangrove
5.32
Unclassed Forests
7
Mangrove
2.4812
Proposed Reserved Forests (Sec-4 of IFA)
Total
22.9648
Division 1. : Alibag
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Raigad
15.3616
Total
15.3616
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
12.0432
0.4
Eco 2
2
3.1204
0.2
Eco 1
Total.
15.1636
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Others
Manvrove species, Ain, Teak, Swawar, Kinjal, Shemat, Karanj, Wad
8988
2190
499
0
0
0
Total
8988
2190
499
0
0
0
Sub Total (No of Trees.)
11677
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
The project area is not vulnerable to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NIL
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
395.26626
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
4
Reserved Forest under Section 4 of IFA
Karjat East
S,No. 23/0
View file
2
2
4
Reserved Forest under Section 4 of IFA
Karjat East
S,No. 23/0
View file
3
3
13
Reserved Forest under Section 4 of IFA
Karjat East
S.No. 37
View file
4
4
15
Reserved Forest under Section 4 of IFA
Panvel
S.No. 62, 65 (old S.No. 61 and 64)
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Alternative Alignment certificate of DCF
2
Chronological events
3
Distance from Protected area
4
NPV certificate
5
Tree felling Estimate
6
Tree cutting certificate
7
Identified Forest Certificate
8
Archaeological certificate
9
Document Verification certificate of DCF
10
Information furnish in English
11
List of Identified forest
12
No violation certificate
13
Wildlife certificate
Division 2. : Mangrove
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Mumbai (Suburban)
7.8012
Total
7.8012
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
7.8012
0.4
Eco 2
Total.
7.8012
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
NA
6.
Brief note on vulnerability of the forest area to erosion :
The area is not vulnerable and there is no possiblity of erosion. The slop of area is plain and topography of area is mudflat.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
The distance from TCFS is 5.5 KM and SGNP is 11.2 Km.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
Yes
Details of Protected Area and comments on the impact of Project on the ESZ :
The proposed project alignment is outside the proposed ESZ area of Thane Creek Flamingo Sanctuary. Therefore the project does not have any adverse effect on any species of Flora and Fauna within the area.
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
NO Data
Additional information Details
S. No.
Documents
Remarks
1
NPV certificate of DFO MMCU
2
Certificate of identified forest of DFO MMCU
3
area statement of DFO MMCU
4
undertaking of cost of removal of shrub exploitation of user agency.
5
archeological certificate of DFO MMCU
6
Wildlife certificate of DFO MMCU
7
No violation certificate of DFO MMCU
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Mumbai (Suburban)
44600
3948.0817
2.4578
6
0
31/03/2019
0
0
2
Raigad
715200
164768
1222.4483
89
2113.0954
31/03/2019
2113.0954
367.4640
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Alibag
Thane
DFO
Yes
One
05/02/2020
Mangrove
CF
No
No Data
Thane
CF
No
No Data
Mangrove
Mangrove
DFO
Yes
One
23/08/2019
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Alibag
Thane
DFO
Recommended
This proposal is for construction of underground Petroleum products pipeline with OFC and associated facilities from Mahul Mumbai Suburban District to Rasayani Raigad District is a safe mode of transportation of petroleum product that leads to reduce road congestion, lower energy consumption and is environmental friendly by minimizing gaseous emission in transit. The proposed pipeline is for public utility and for supply of aviation fuel to proposed Navi Mumbai International Airport. This project is recommended as this is an infrastructure development and public utility project. Project proponent is ready to bear all the Government levies hence the proposal is being recommended for approval for diverting the required forest land under Forest Conservation Act, 1980.
Mangrove
Mangrove
DFO
Recommended
The project is recommended as the pipeline is safe mode of transportation, reduce road congestion, lower energy consumption and environmental friendly by minimizing gaseous emission in transit. The proposed pipeline is for public utility and supply of aviation fuel to proposed Navi Mumbai International Airport and after completion of project the diverted land is resorted back to its normal condition by project proponent.
Mangrove
CF
Recommended
The proposed project is for public utility, environmental friendly and for supply of aviation fuel to proposed Navi Mumbai International Airport. After the completion of project the diverted land should back to its normal condition by the project proponent.
Yes
Thane
CF
Recommended
Part 3 and ccf covering letter attached
Yes
Nodal Officer
Recommended
recommendation
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Maharashtra
State Secretary
Recommended
26/03/2021
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Nagpur
Regional Office
FC-II/MH-163/2021-NGP
10/08/2022
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MH/Pipeline/39455/2019
PIPELINE394552019378
71,351,967.00
71,351,967.00
24/08/2023
110045
Union Bank Of India
NEFT/RTGS (Challan)
12/06/2023
13/06/2023
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
46
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
4
No. of patches :
2
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
2
Block(Polygon)
15
Status of CA Land so identified :
Forest Area
Site Name :
Morbe , Panvel
Location Details :
S. No. 61 & 64
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Morbe
RF
No. of patches :
3
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
3
Block(Polygon)
8
Status of CA Land so identified :
Forest Area
Site Name :
Kashele , Karjat
Location Details :
S no -23
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Kashele
RF
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
10
Status of CA Land so identified :
Forest Area
Site Name :
Palaspe, Panvel
Location Details :
S no. 76
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Palaspe
RF
No. of patches :
4
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
4
Block(Polygon)
13
Status of CA Land so identified :
Forest Area
Site Name :
Dahigaon and Vengaon, Karjat
Location Details :
Dahigaon s no. 60/1/B Vengaon s no 13/1/A
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Dahigaon and Vengaon
PF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/MH/Pipeline/39455/2019
20 Sep 2023
No Data
Verify
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/MH/Pipeline/39455/2019
20 Sep 2023
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/MH/Pipeline/39455/2019
Recommended
01 Dec 2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MH/Pipeline/39455/2019
22 Dec 2023
APPROVED
Print
Checklist for State Nodal Officer
×