PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MH-060/2022
1.
Location of the project/Scheme :
Maharashtra
(i)
State / Union Territory :
Maharashtra
(ii)
District :
Raigad
(iii)
Forest Division :
Alibag
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.0085
 (v)
Category of the Proposal:
Pipeline
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Alibag
0.0016
Protected Forest
2
Alibag
0.0069
Reserved Forest
Total
0.0085
Division 1. : Alibag
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Raigad
0.0085
Total
0.0085
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.0085
0
Eco 1
Total.
0.0085
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Misc. Species
Nil
0
0
0
0
0
0
Total
0
0
0
0
0
0
Sub Total (No of Trees.)
0
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
The project area is not vulnerable to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Nil
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
22.45228
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
1
RF
Pen
58/1
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
chronological events
2
identified forest certificate
3
identified list
4
information furnished in english
5
archeological importance certificate
6
distance from protected area
7
violation certificate
8
wildlife certificate
9
alternative examination certificate
10
cutting of trees certificate
11
absence of alternative alignment certificate
12
NPV certificate
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Raigad
715200
164768
1300.0955
97
2113.0954
31/03/2022
367.4640
367.4640
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Alibag
Thane
DFO
Yes
One
27/10/2022
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Alibag
Thane
DFO
Recommended
This proposal is for non Forest activities i.e., laying 10” Dia LPG underground pipeline along with OFC in Protected and Reserved Forest land. This project is infrastructure and public utility project. The Project proponent is ready to bear all the Government levies hence the proposal is being recommended for approval for diverting the required forest land under Forest Conservation Act, 1980.
Thane
CF
Recommended
Recommended for forwarded for acceptance and necessary approval under the Provisions of the Forest Act,1980.
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Maharashtra
State Secretary
Recommended
22/05/2023
FLD 1323/CR107/F 10, Stage I approval accorded by GoM
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Nagpur
State Government
FLD-1323/CR107/F-10
16/05/2023
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MH/Pipeline/147671/2021
PIPELINE1476712021384
814,378.00
814,378.00
17/08/2023
86426
Union Bank Of India
NEFT/RTGS (Challan)
10/07/2023
12/07/2023
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
1
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
1
Status of CA Land so identified :
Forest Area
Site Name :
Borivali
Location Details :
Borivali, Raigad dist.
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Reserved Forest
RF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/MH/Pipeline/147671/2021
04 Oct 2023
No Data
verified
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/MH/Pipeline/147671/2021
16 Oct 2023
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/MH/Pipeline/147671/2021
Recommended
15 Dec 2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MH/Pipeline/147671/2021
05 Feb 2024
APPROVED
Print
Checklist for State Nodal Officer
×