PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MH-074/2021
1. Location of the project/Scheme : Maharashtra
 (i) State / Union Territory : Maharashtra  (ii) District : Thane  (iii) Forest Division : Shahapur  (iv) Area of forest land proposed for diversion (in ha.) : 2.3238  (v)

Category of the Proposal: Pipeline
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Shahapur0.7591Reserved Forest
2Shahapur1.4024Protected Forest
3Shahapur0.1623Private Forest
Total 2.3238
Division 1. : Shahapur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Thane2.3238
Total2.3238
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.75910.3Eco 1
21.40240.3Eco 1
30.16230.1Eco 1
Total. 2.3238


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Tectona GrandisTeak3010422210
2Acacia CatechuKhair110000
3Terminalia TomentosaAin85172651420
4OthersMixed species10024980291210
Total 216 526167 4515 10
Sub Total (No of Trees.) 979


5. Working plan prescription for the forest land proposed for diversion : Tropical Moist Deciduous Forest
6. Brief note on vulnerability of the forest area to erosion : The area does not form a part of serious eroded area hence there is no possibility of erosion. Still the project authority take precaution that, construction activities in diverted
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No rare/ endangered/ unique species of Flora and Fauna found in the proposed forest area during the site inspection.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): Yes
  Details of Protected Area and comments on the impact of Project on the ESZ : The nearest Tansa Wildlife Sanctuary is located at 1.475 km away from project boundary.
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 38.32780
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
115.00Protected ForestShahapur0    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Part II
2 Covering Letter
3 Joint Inspection Report
4 Tree Felling Certificate
5 Wildlife Certificate
6 CA non forest land certificate
7 NPV Certificate

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Thane135778.9056799.964336.2982341209.13631/10/20221209.13636.605
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
ShahapurThaneDFOYesOne27/07/2022
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
ShahapurThaneDFO RecommendedThe proposed pipeline route is the most suitable route from Mumbai to Nagpur, as the forest land is already diverted to MSRDCL for Nagpur Mumbai Super Communication Expressway Package V for laying underground petroleum pipeline from Mumbai to Manmad and the proposed Natural Gas Pipeline is passing through the RoW of MSRDCL. But in some patches it is not feasible to work in the existing Right of Way of Nagpur – Mumbai Samruddhi Expressway. So the project authority has proposed diversion in the said patches, which requires new forest land. Hence the proposal for diversion is recommended for acceptance as per the Specific Recommendation enclosed with Part II.
ThaneCF RecommendedProposal recommended and forwarded for acceptance and necessary approval under section 2 of Forest Conservation Act 1980.Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MaharashtraState SecretaryRecommended20/04/2023FLD 1223/CR97/F 10, Recommended for approvalState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
NagpurRegional OfficeFC-I/MH-326/2023-NGP28/04/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MH/Pipeline/140171/2021PIPELINE14017120216427,592,555.007,592,555.0023/05/2023958959Union Bank Of IndiaNEFT/RTGS (Challan)23/05/202323/05/2023
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 5   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)5
  Status of CA Land so identified : Forest Area   Site Name : District: Thane Division, Range & Taluka: Shahapur Round: Shera Village: Shei Gut No.: 156 Survey No.: 99   Location Details : District: Thane Taluka: Shahapur Village: Shei Gut No.: 156 Survey No.: 99   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Degraded Forest land in Shahapur Division of Shei VillagePF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/MH/Pipeline/140171/202126 May 2023No DataVerified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/MH/Pipeline/140171/202126 May 2023
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/MH/Pipeline/140171/2021Recommended21 Jun 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MH/Pipeline/140171/202111 Sep 2023APPROVED