PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
MH-0123/2015
1.
Location of the project/Scheme :
Maharashtra
(i)
State / Union Territory :
Maharashtra
(ii)
District :
Raigad
(iii)
Forest Division :
Alibag
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.8878
 (v)
Category of the Proposal:
Others
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Alibag
0.8878
Reserved Forest
Total
0.8878
Division 1. : Alibag
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Raigad
0.8878
Total
0.8878
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.8878
0.4
Eco 1
Total.
0.8878
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Acacia Catechu
Khair
0
4
0
0
0
0
2
Others
Superier Injayali
0
1
1
0
0
0
3
Others
Infairial Injayali
0
7
4
2
0
0
Total
0
12
5
2
0
0
Sub Total (No of Trees.)
19
5.
Working plan prescription for the forest land proposed for diversion :
--
6.
Brief note on vulnerability of the forest area to erosion :
The pipeline is laid in trenches about 1.5 meter depth x 2 meter wide and ROU of 10 metres. After laying of pipeline, the forest can be regrown on the ROU and no further disturb.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.00
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NIL
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
1156492
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
1.7756
PF
Alibag
PF Gut No. 143
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Raigad
715200
164768
929.4104
78
2068.183
31/03/2016
2009.9538
367.464
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Alibag
Thane
DFO
Yes
One
19/09/2016
Thane
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Alibag
Thane
DFO
Recommended
The trees to be felled is less than the trees which was required to be felled in main proposal, hence the proposal is being recommended for approval (as per guidelines para No. 2.1) for diverting the additional required forest land in change in alignment under Forest (Conservation) Act, 1980
Thane
CF
Recommended
Yes
Nodal Officer
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Maharashtra
State Secretary
Recommended
08/02/2017
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Nagpur
Regional Office
6-MHC033-2014-BHO
30/06/2017
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/MH/Others/15741/2015
OTHERS157412015688
2,382,045.00
10.00
06/07/2017
SIN00354Q4970039
Corporation Bank
NEFT/RTGS (Challan)
04/07/2017
04/07/2017
FP/MH/Others/15741/2015
OTHERS157412015688
2,382,045.00
2,382,045.00
11/07/2017
SIN00354Q4976142
Corporation Bank
NEFT/RTGS (Challan)
NA
NA
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/MH/Others/15741/2015
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×