PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : MH-010/2021
1. Location of the project/Scheme : Maharashtra
 (i) State / Union Territory : Maharashtra  (ii) District : Nagpur  (iii) Forest Division : Nagpur  (iv) Area of forest land proposed for diversion (in ha.) : 15.811  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Nagpur15.811Zudpi jungle
Total 15.811
Division 1. : Nagpur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Nagpur15.811
Total15.811
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
115.8110.4Eco 3
Total. 15.811


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Acacia leucophloeaHiwar001000
2Butea MonospermaPalas112439100
3Azadirachta IndicaKadunimb02514300
4Tectona GrandisSaag2648000
5Othersothers0188530
6Butea MonospermaPalas1125612200
7Azadirachta IndicaKadunimb02415300
8Tectona GrandisSaag2648000
9Othersothers0218630
10Acacia NiloticaBabool16310000
Total 27 77893 206 0
Sub Total (No of Trees.) 924


5. Working plan prescription for the forest land proposed for diversion : no
6. Brief note on vulnerability of the forest area to erosion : The Forest land involved in the project is not prone to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.442
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : NO
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 400
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1125.80Zhudpi JungleButiboriButibori    View file
229.997PFButiboriRound Kuhi    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 CA CERTIFICATE
2 PART 2

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Nagpur9931002401115280.5641156906.2222/06/202137.350.00
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
NagpurNagpurDFO RecommendedRecommended for approval
NagpurCF RecommendedRecommended for approval Yes
Nodal Officer RecommendedRecommended.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
MaharashtraState SecretaryRecommended23/03/2022Recommended for approval if it is a linear projectState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
NagpurRegional OfficeFC-II/MH-180/2022-NGP02/05/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/MH/Others/118188/2020OTHERS118188202063863,787,444.0063,787,444.0010/05/2022SBIN512982858406Union Bank Of IndiaNEFT/RTGS (Challan)06/05/202209/05/2022
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 35.997   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 2
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)9.997
  Status of CA Land so identified : Forest Area   Site Name : Bhojapur   Location Details : North Umred   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
NagpurPF
  No. of patches : 2
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
2Block(Polygon)25.8
  Status of CA Land so identified : Forest Area   Site Name : Butibori Sukli   Location Details : Survey No.21   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
NagpurPF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/MH/Others/118188/202027 May 2022No DataCA proposed on degraded forest land
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/MH/Others/118188/202030 Jan 2023
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/MH/Others/118188/202020 Jul 2022EDS: for query compliance04 Oct 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/MH/Others/118188/2020Recommended27 Jul 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/MH/Others/118188/202031 Jan 2023APPROVED