PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : LA-08/2023
1. Location of the project/Scheme : Ladakh
 (i) State / Union Territory : Ladakh  (ii) District : Kargil  (iii) Forest Division : Kargil  (iv) Area of forest land proposed for diversion (in ha.) : 0.3625  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Kargil0.3625Protected Forest
Total 0.3625
Division 1. : Kargil
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Kargil0.3625
Total0.3625
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.36250.4Eco 6
Total. 0.3625


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Populus sppZyarpa220160181200
Total 220 16018 120 0
Sub Total (No of Trees.) 410


5. Working plan prescription for the forest land proposed for diversion : As per the working plan the proposed diversion area i.e Khandiyal Lungma and Ghoshon Ralam of Drass headquarter bead is proposed under degraded Forest working conservation and Plantation working circle Kargil Forest Division ( UT Ladakh)
6. Brief note on vulnerability of the forest area to erosion : The hilly tophography of forest land involved in the applied mining lease, will result in soil erosion following felling trees.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Ibex, Wolf, Himalayan Fox etc found in the adjacent mountain.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 27.63515
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
111.50AbranZanskarAbran -2    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Clarification regarding CA land
2 CA Alignment marked on SOI Map
3 CA Plan
4 Detail Estimate of Compensatory Afforestation (CA) at the alternate land alloted by Deputy Commissioner Kargil at Abran Zansakr.
5 NPV Calculation
6 Site inspection report
7 alignment marked on SOI Map
8 CA land suitability.
9 Undertaking for payment of NPV and CA and Approval of Project
10 Recommendation of DFO
11 DGPS map of CA Land
12 Under taking for payment of CA and NPV and approved project.
13 CA Norms
14 Legal status of CA land (transfer/ Allotment of State land to Forest Deptyt Kargil.

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Kargil14036006478910.362506/03/20240.362548.4535
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
KargilLadakh CircleDFOYesOne12/07/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
KargilLadakh CircleDFO RecommendedRecommended
Ladakh CircleCF RecommendedRecommendedYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
LadakhState SecretaryRecommended27/12/2023 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
JammuRegional Officeo 9-JKA-001/2024-Jammu04/10/2024
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/LA/ROAD/152696/2022ROAD15269620224381,514,313.001,514,310.0025/10/2024CNRBR52024102591691961Union Bank Of IndiaNEFT/RTGS (Challan)10/10/202410/10/2024
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 1.5   (iii). No. of Maintenance years: 11   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)1.5
  Status of CA Land so identified : Non Forest Area   Site Name : NIL   Location Details : NIL   Uploaded GPS File :   Uploaded Scanned copy of Map :   Whether land Mutated or not : No
Status of CA Land so identified
District Name. Name of Tehsil.
KargilZanskar
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/LA/ROAD/152696/202217 Apr 2025No Dataverified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/LA/ROAD/152696/202229 May 2025
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/LA/ROAD/152696/2022Recommended02 Jun 2025
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/LA/ROAD/152696/2022Approved In-PrincipleNo Data