PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : KL-025/2018
1. Location of the project/Scheme : Kerala
 (i) State / Union Territory : Kerala  (ii) District : Thiruvananthapuram  (iii) Forest Division : Thiruvananthapuram WL  (iv) Area of forest land proposed for diversion (in ha.) : 0.21  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Thiruvananthapuram WL0.21Protected Forest
Total 0.21
Division 1. : Thiruvananthapuram WL
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Thiruvananthapuram0.21
Total0.21
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.210.2Eco 3
Total. 0.21


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The proposed area is for the construction of a bridge across Neyyar reservoir and hence there is no vulnerability to erosion .
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Elephant,Gaur,Smabar deer,leopard, Wild boar etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : The proposed area is lying on the fringe of Neyyar Wildlife Sanctuary. Since the bridge is to constructed at Kombichalkadavu across Neyyar reservoir, there is little impact on the eco system of the sanctuary
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): Yes
  Details of Protected Area and comments on the impact of Project on the ESZ : The project area is lying on the fringe of Neyyar Wildlife Sanctuary.Since the bridge is to constructed at Kombichalkadavu across Neyyar reservoir, there is little impact on the eco system of the sanctuary
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 0
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.39Neyyar Wildlife Sanctuary NeyyarKarikuzhy    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Thiruvananthapuram2192003686000028/07/201800
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Thiruvananthapuram WLAgastyavanam Biological Park Circle, ThiruvananthaDFOYesTwo31/05/2018,26/06/2018
 Agastyavanam Biological Park Circle, ThiruvananthaCFYesOne28/07/2018
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Thiruvananthapuram WLAgastyavanam Biological Park Circle, ThiruvananthaDFO RecommendedThe bridge is to be constructed at kumbichalkadavu across Neyyar Reservoir in Neyyar Wildlife Sanctuary.The bridge will provide vehicular traffic to about 400 families of 11 tribal settlements on other side of Neyyar reservoir. This is the only way to connect the people outside. The proposal will not adversely affect the wildlife. Hence recommended for Forest clearance.
Agastyavanam Biological Park Circle, ThiruvananthaCF RecommendedThe bridge will provide vehicular traffic to about 400 families of 11 tribal settlements on either side of Neyyar Reservoir.At present there is a ferry operating in the reservoir and it is very difficult to operate the same during rainy season.Klamala- I Section office of Neyyar Wildlife sanctuary is also functioning on the other bank of reservoir.The bridge is very much useful for the department and the local inhabitants who are tribals.The proposal will not adversely affect the wildlife.HenceYes
Nodal Officer RecommendedThe bridge is to be constructed at Kumbichalkadavu across Neyyar Reservoir in Neyyar Wildlife Sanctuary.The bridge will provide vehicular traffic to about 400 families of 11 tribal settlements on other side of Neyyar Reservoir.This is the only way to connect the people outside.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
KeralaState SecretaryRecommended15/09/2020 RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BangaloreState GovernmentC3/70/2019/FWLD14/09/2020
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/KL/Others/32487/2018OTHERS3248720189191,095,150.001,095,150.002022-05-09SBIN512882650478Union Bank Of IndiaNEFT/RTGS (Challan)2022-04-262022-04-27
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/KL/Others/32487/201809 Jun 2022No Dataverify and found correct
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/KL/Others/32487/201809 Jun 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/KL/Others/32487/2018The proposal may be considered and accorded stage II clearance at the earliest.13 Apr 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/KL/Others/32487/201808 May 2023APPROVED