PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : KA-038/2015
1. Location of the project/Scheme : Karnataka
 (i) State / Union Territory : Karnataka  (ii) District : Mangalore  (iii) Forest Division : Mangalore  (iv) Area of forest land proposed for diversion (in ha.) : 0.03  (v)

Category of the Proposal: Drinking Water
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Mangalore0.03Reserved Forest
Total 0.03
Division 1. : Mangalore
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Mangalore0.03
Total0.03
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.030.6Eco 1
Total. 0.03


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The forest is not vulnerable to erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Wild animals such as wild boar and ungulates are found in the forest area.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 0
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.405kalanjimale Reserve forestPuttur0    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Mangalore420860.87113398.69118.7627100.03919/03/2016183.59121.484
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
MangaloreMangaloreDFOYesOne17/03/2016
 MangaloreCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
MangaloreMangaloreDFO RecommendedThe project requires 0.1054 ha area which is located in an acacia plantation and that to along an existing cart road, requiring no trees to be felled, the proposal may be considered for clearance under Forest (Conservation) Act 1980.
quetiapin ritalin quetiapin und valdoxan quetiapin wirkstoff
MangaloreCF RecommendedThe project proponent has requested forest land for construction of drinking water tank and laying pipeline. The area proposed is 0.1054 ha. As the work site is Acacia plantation and it does not involve any cutting of trees the proposal is recommendedYes
Nodal Officer RecommendedRecommended for diversion of 0.1054 ha. of forest land in Bantwal Taluk, D.K. District to provide safe drinking water to 80 habitations which caters to around 3800 SC & ST population among others in favour of the Executive Engineer, Rural Drinking water Supply and Sanitation Department, Mangaluru under the Forest (Conservation) Act, 1980 subject to the specific condition & conditions appended in Annexure ‘A’.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
KarnatakaState SecretaryRecommended20/04/2017 Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
BangaloreState GovernmentFEE 87 FLL 201604/11/2016
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/KA/WATER/15630/2015WATER15630201586758,264.0058,264.002023-02-2730870Union Bank Of IndiaNEFT/RTGS (Challan)2023-02-202023-02-22
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/KA/WATER/15630/201513 Apr 2023No Dataplease upload the compliance report
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/KA/WATER/15630/201510 Jan 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/KA/WATER/15630/2015the compliance report is here by attached for your information and further necessary action17 Jan 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/KA/WATER/15630/2015IN-PRINCIPLENo Data