PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
KA-079/2017
1.
Location of the project/Scheme :
Karnataka
(i)
State / Union Territory :
Karnataka
(ii)
District :
Tumkur
(iii)
Forest Division :
Tumkur
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.8955
 (v)
Category of the Proposal:
Transmission Line
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Tumkur
0.895
Reserved Forest
Total
0.895
Division 1. : Tumkur
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Tumkur
0.895
Total
0.895
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.895
3
Eco 3
Total.
0.895
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Azadirachta Indica
Bevu
0
18
0
0
0
0
2
Bamboo
Bidiru
0
1
0
0
0
0
3
Erythrina Indica
Devadarau
0
5
0
0
0
0
4
Zizyphus Jujuba
Elachi
0
1
0
0
0
0
5
Ficus Mysorensis
Hatti
0
1
0
0
0
0
6
Madhuka Indica
Hippe
0
7
0
0
0
0
7
Pongamia Pinnata
Honge
0
97
0
0
0
0
8
Pterocarpus Marsupium
Honne
0
3
0
0
0
0
9
Garcinia Combogia
Kadubikke
0
6
0
0
0
0
10
Cassia Fistula
Kakke
0
2
0
0
0
0
11
Hardwickia Binnata
Kamara
0
11
0
0
0
0
12
Butea Monosperma
Muttuga
0
2
0
0
0
0
13
Acacia leucophloea
Nayi Bela
0
1
0
0
0
0
14
Cassia Siamea
Seemetangadi
0
21
0
0
0
0
15
Dalburgia Sisoo
Sisu
0
2
0
0
0
0
16
Acacia Catechu
Taredu
0
45
0
0
0
0
17
Albezzia Amara
Tuggali
0
12
0
0
0
0
18
Syzigium Sps
Udaya
0
2
0
0
0
0
Total
0
237
0
0
0
0
Sub Total (No of Trees.)
237
5.
Working plan prescription for the forest land proposed for diversion :
0.895
6.
Brief note on vulnerability of the forest area to erosion :
The forest is poor and open due to over explitation in the past and much of the area is covered with scrub type of thorny species.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.04
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Rabbit, Bear, Cheetah, Peacock and other local animals
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
18.00
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
6.00
RF
Gubbi
4
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
2
3
4
5
6
7
8
9
10
11
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Tumkur
1059800
112555
313.643
17
61
31/03/2017
00
145.32
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Hassan
CF
Yes
One
30/11/2017
Tumkur
Hassan
DFO
Yes
One
19/12/2017
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Tumkur
Hassan
DFO
Recommended
Alternate feasible routes were studied based on premlinary/ walkover survey keeping in view of length of lines, number of angle points, power line crossing and other statutory clearances. Upon detailed study, the proposed laying of UNDER GROUND cable of 66kv found to be generally feasible and with minimum infringement with the already existing permanent features and least inconvenience to habitat at large. Moreover circumventing of forest area comes to more than 35 k.m which mostly consist of a
Hassan
CF
Recommended
Inspected the site on 14-11-2017 and having agreed with the recommendations of DCF, Tumkur Division proposal is recommended for acceptance in the best public interest. A detailed Inspection note in the form of covering letter dated 30-11-2017 has been enclosed
Yes
Nodal Officer
Recommended
Submitted for approval for diversion of 0.8955 ha of forest land in Ankasandra State Forest (Sy. No. 16 & 17 of Kurubarahalli Village and Sy. No. 19 of Thalekoppa Village) in Gubbi Taluk, Tumkuru District for laying 66 KV underground cable (transmission line) for 20 MW solar plant at Telekoppa Village, Gubbi Taluk, Tumkuru District in favour of M/s. Adani Green Energy (UP) Ltd., Bengaluru under the Forest (Conservation) Act, 1980 subject to compliance under RoFR Act, 2006 and conditions listed
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Karnataka
State Secretary
Recommended
29/01/2018
RECOMMENDED
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Bangalore
Regional Office
4-KRB1139/2018-BAN
01/02/2018
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/KA/TRANS/28661/2017
TRANS286612017537
2,960,583.00
2,960,583.00
16/02/2018
AXSK180460032534
Corporation Bank
NEFT/RTGS (Challan)
NA
NA
FP/KA/TRANS/28661/2017
TRANS286612017537
2,960,583.00
160,000.00
27/07/2018
153691
Corporation Bank
NEFT/RTGS (Challan)
15/02/2018
15/02/2018
FP/KA/TRANS/28661/2017
TRANS286612017502
1,695,000.00
1,695,000.00
13/01/2022
BARC101213700146
Union Bank Of India
NEFT/RTGS (Challan)
05/01/2022
10/01/2022
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
6
(iii). No. of Maintenance years:
12
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
6
Status of CA Land so identified :
Forest Area
Site Name :
Sy.No.16 of Ammanghatta Village, Kasaba Hobli, Gubbi Taluk, Tumkur District.
Location Details :
Sy.No.16 of Ammanghatta Village, Kasaba Hobli, Gubbi Taluk, Tumkur District.
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Ammanghatta State Forest
Other Forest Land
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/KA/TRANS/28661/2017
03 May 2018
No Data
Accepted.
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/KA/TRANS/28661/2017
25 Feb 2022
Compliance Details Submitted by User Agency(old)
Proposal No.
Compliance Details submitted on(Date)
Reject Remarks
Reject Date
Uploaded Letter
FP/KA/TRANS/28661/2017
01 Dec 2021
EDS: Demand notice uploaded instead of Condition Wise Compliance Report. Hence, please reply to GoK EDS query on 28-10-2021. Then submit the Compliance Report
01 Dec 2021
FP/KA/TRANS/28661/2017
03 May 2018
EDS: Please obtain demand notice for differential CA charges from DCF, Tumakuru Division and upload through online for further processing
12 Nov 2021
FP/KA/TRANS/28661/2017
02 Dec 2021
EDS: you are requested to obtain a supplementary demand notice from DCF Tumakur towards differential Compensatory planting charges and upload generate the challan
14 Dec 2021
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/KA/TRANS/28661/2017
29 Oct 2020
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/KA/TRANS/28661/2017
17 Nov 2022
APPROVED
Print
Checklist for State Nodal Officer
×