PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
KA-0121/2022
1.
Location of the project/Scheme :
Karnataka
(i)
State / Union Territory :
Karnataka
(ii)
District :
Gadag
(iii)
Forest Division :
Gadag
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.063
 (v)
Category of the Proposal:
Pipeline
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Gadag
0.063
Reserved Forest
Total
0.063
Division 1. : Gadag
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Gadag
0.063
Total
0.063
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.063
0.2
Eco 4
Total.
0.063
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Eucalyptus Sps
Nilgiri
1
0
0
0
0
0
Total
1
0
0
0
0
0
Sub Total (No of Trees.)
1
5.
Working plan prescription for the forest land proposed for diversion :
The proposed area is part of Protection-cum-improvement circle of Working Plan.
6.
Brief note on vulnerability of the forest area to erosion :
The project proposed is along the existing road. The pipeline will be laid and the excavated soil will be relaid on the pit so there is no possibility of erosion in the said area.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Blackbuck, spotted deer, hyena, jackal, fox, wolf, porcupine, leopard, ant eater, four horned antelope etc.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
Yes
Details of Protected Area and comments on the impact of Project on the ESZ :
The proposed area for diversion is within the buffer area of proposed ESZ and within 10 KMS deemed ESZ as per the Orders of the Honourable Surpreme Court. The project will not have any major impact on the PA because the pipeline will be laid all along the existing road. After the laying of pipeline, the excavated area will be refilled and made good just as it was there previously.
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
Yes
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
NO Data
(ii).
Copy of CA scheme details:
NA
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority:
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Gadag
465600
32442.124
417.406
14
0
09/09/2022
0
62.783
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Gadag
Dharwad
DFO
Yes
One
17/08/2022
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Gadag
Dharwad
DFO
Recommended
The diversion is proposed for laying of pipeline for water supply to Shingtrayankere tank under the lift irrigation scheme of 4072 Special Component Plan so that it serves as a perennial source of water for irrigation and other non potable needs of the village. It also aims at recharging the groundwater and there by improving the overall groundwater profile of the area.
Dharwad
CF
Recommended
The proposal received for Diversion of 0.063 Ha. Of Forest land for constuction of pipeline in Papanashi Sy.No.34 of Gadag Taluka and Sy No. 80/1A/1 of Singtarayankere Village Mundaragi Taluk Gadag Dist. For water supply to Singtarayanakere tank in Mundaragi Taluka in Favour of AEE Minor Irrigation & GWD Sub Division Gadag. Proposal No.FP/KA/Pipeline/154978/2022 from minor irrigation dept. through The Deputy Conservator Of Forests Gadag Division is enclosed herewith for your kind information & furthur needful action. hard copy of proposal 4 sets sent through REGISTER POST
Yes
Nodal Officer
Recommended
Justified in letter
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Karnataka
State Secretary
Recommended
16/01/2023
Stage I Approval
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Bangalore
State Government
FEE 139 FLL 2022
16/01/2023
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/KA/Pipeline/154978/2022
PIPELINE1549782022171
340,713.82
340,714.00
2023-11-28
RBI3332312574906
Union Bank Of India
NEFT/RTGS (Challan)
NA
NA
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/KA/Pipeline/154978/2022
17 Aug 2024
No Data
Verified
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/KA/Pipeline/154978/2022
IN-PRINCIPLE
No Data
Print
Checklist for State Nodal Officer
×