PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
KA-05/2017
1.
Location of the project/Scheme :
Karnataka
(i)
State / Union Territory :
Karnataka
(ii)
District :
Bagalkot
(iii)
Forest Division :
Bagalkot
 (iv)
Area of forest land proposed for diversion (in ha.) :
3.3
 (v)
Category of the Proposal:
Industry
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Bagalkot
3.3
Reserved Forest
Total
3.3
Division 1. : Bagalkot
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Bagalkot
3.3
Total
3.3
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
3.3
0.1
Eco 4
Total.
3.3
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Ficus Religiosa
Arali
7
2
1
0
0
0
2
Zizyphus Jujuba
Baremara
1
0
0
0
0
0
3
Ficus Bengalensis
Basari Mara
0
3
1
0
0
0
4
Others
Limonia acidissima
3
1
0
0
0
0
5
Azadirachta Indica
Bevu
181
106
25
1
0
0
6
Others
Halagatti
1
0
0
0
0
0
7
Ficus Racemosa
Hatti Mara
1
0
0
0
0
0
8
Mammea Longifolia
Hippe mara
2
0
0
0
0
0
9
Pongamia Pinnata
Honge Mara
47
2
0
0
0
0
10
Others
Balanites roxburghii-Ingala
1
2
0
0
0
0
11
Others
Vachellia nilotica-KariJali(Local Name)
3
0
0
0
0
0
12
Others
Canthium parviflorum Lam-Karemara
1
0
0
0
0
0
13
Others
Carissa carandas-Kavli
1
00
0
0
0
0
14
Samania Saman
Malemara
1
0
0
0
0
0
15
Others
Mashwala
69
14
0
0
0
0
16
Ecocarpus Spp.
Nilagiri
4
4
0
1
0
0
17
Others
Sterculia urens-Tapsi
1
1
0
0
0
0
18
Others
Terminalia elliptica-Tugali
16
04
0
0
0
0
19
Others
Shrubs
1866
0
0
0
0
0
Total
2206
139
27
2
0
0
Sub Total (No of Trees.)
2374
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
Plane area hence there is no erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Hyenas, Indian Fox, Porcupine, Black Naped Hare
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
Yes
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
Yes
(a)Details of violation(s):
KFR-1963
(b) Period of Work done(year) :
00
(c) Area of forest land involved in violation (in ha.) :
1.216
S. No.
Name of person responsible for violation
Designation & Address of person responsible for violation
Action taken against the person responsible for violation
1
Senior General Manager
Gem Sugars ltd Kundaragi
FIR filed
12.
Whether work in violation is still in progres(Yes/No) :
No
13.
Details of compensatory afforestation scheme
(i).
Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no
District Name
Village
Area(in ha.)
khasra
KML file
Present Owner file
1
Bagalkot
Hanagandi Village of Jamkandi taluk Dist : Bagalkot
2.933
Not applicable
(ii).
Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iii).
Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A:
(iv).
Copy of CA scheme details:
NA
Additional information Details
S. No.
Documents
Remarks
1
violation report
2
Certificate
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Bagalkot
659300
78902.372
129.304
33
78.768
18/12/2023
73.748
5.69
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Bagalkot
Belgaum
DFO
Yes
One
01/11/2023
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Bagalkot
Belgaum
DFO
Recommended
The demand for forest land is minimum and hence this proposal is recommended
Print
Checklist for State Nodal Officer
×