PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : JK-010/2021
1. Location of the project/Scheme : Jammu and Kashmir
 (i) State / Union Territory : Jammu and Kashmir  (ii) District : Kishtwar  (iii) Forest Division : Marwah Forest Division  (iv) Area of forest land proposed for diversion (in ha.) : 5.9312  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Marwah Forest Division5.9312Reserved Forest
Total 5.9312
Division 1. : Marwah Forest Division
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Kishtwar5.9312
Total5.9312
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
15.93120.5Eco 6
Total. 5.9312


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1PineDeodar (Cedrus deodara)6876977385372
2PineKail (Pinus wallichiana)485741111468
3PineFir/Spruce (Abies pindrow)000010
4PineChilgoza (Pinus gerardiana)00011016
5PoplusPoplar (Poplus spp)000005
6Juglan RegiaWalnut000003
7OthersHC Nut (Aesculus indica)356545382863
8OthersBrari (Ulmus wallichiana)1001414
9OthersAsh (Fraxinus excelsior)002191172
10OthersUrni (Corylus avellana)013640
11OthersTrikana ( Acer spp)4035311091
12OthersKharak (Celtis australis)321442
13Rhus Spp.Arkhad (Rhus succedania)302924573
14OthersGir (Corylus jacquemontii)001000
15OthersBran (Ulmus wallichiana)000002
16OthersKellar (Parrotia jacquemontiana)1105641200
17OthersChamp (Almus nitida)603832013
Total 395 359318 170178 624
Sub Total (No of Trees.) 2044


5. Working plan prescription for the forest land proposed for diversion : Co 15/D, 13/D, 10/D, 9/D , 8b/D & 8c/D are assigned to the Mixed Conifer Selection working circle. This working Circle includes all commercial forests of Deo and Kail with varying proportions of Fir and Spruce spp. Co. 16b/D and 8a/D are assigned to the Conservation working circle having significant quantum of exploitable growing stock in patches and preserves the pristine ecosystem of the area. Co. 14/D, 12/D & 11/D are assigned to the Fir Selection working circle. These forests consists of mixture of Fir with sprinkling of Spruce Deodar and Kail
6. Brief note on vulnerability of the forest area to erosion : During the Rock cutting some forest erosion is likely to occur as such the User agency has assured to construct the retaining walls
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.01
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Leopard, Musk Deer, Monkeys, Jackals etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 22.75548
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1112Patimhalla ForestDachhan38bD    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Layout plan of construction of Road from Ikhala Block Boundary to Lopara
2 Topo sheet of Construction of Road from Ikhala Block Boundary to Lopara
3 CA plan 38bD
4 SOI Map 38bD
5 Final Notification of Eco Sensitive Zone of KHANP issued under S.O No. 4262 (E) Dt. 13.10.2021 by MoEF & CC
6 Reply of information as asked by Nodal Officer FCA vide his No. PCCF/FCA/3218/1209-10 Dt.26.05.2022
7 Point Wise Information as desired by MoEF & CC
8 Area Statement
9 Enumeration List of Ikhala Block Boundary to Lopara
10 Checklist 16 SIR
11 Checklist 20 Land Suitability
12 Recommendations by DCF
13 Site Specific interventions cum Revised Cost benefit analysis
14 Reply of EDS as sort by IRO Jammu
15 CA approval 38bD
16 Geo Ref Map 38bD
17 EDS in continuation to this office No. 1329 Dt. 23.06.2022
18 Reply of EDS by User Agency
19 Required Information
20 technical feasibility report
21 Animal Passage plan of Ekhala Block boundary
22 Final notification of Eco-sensitive zone of KHANP
23 Joint inspection report
24 Time period
25 NOC of Chief Wildlife Warden in proposal No FP/JK/ROADS /51198/2020
26 Cost of Damage Statement
27 Biological measures
28 Checklist 07
29 Degraded forest
30 Specific recommendation
31 Statement NPV
32 Undertaking CA
33 Undertaking Cost of Damage
34 Undertaking Minimum use
35 Abstract of trees
36 General checklist
37 Undertaking NPV

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Kishtwar773700334006.91529.140639192614/09/202219260
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Marwah Forest DivisionChenab Circle DodaDFOYesOne12/12/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Marwah Forest DivisionChenab Circle DodaDFO RecommendedThe said Road alignment is only possible alignment to connect the 40,000 population of Marwah & Warwan valley to District H.Q Kishtwar. Because in winter season Margan Top remains covered with Heavy snow. Moreover due to construction of this route, migration of local people from Marwah & Warwan Valley should be in favour of upliftment of this remote area. Moreover due to construction of this road accessibility in far flung Kishtwar High altitude would be possible
Chenab Circle DodaCF RecommendedForest land diversion for construction of road from ikhalla block boundary kishtwar to lopara in marwah division is hereby recommended for approval under FCA. Total of 5.9312 hac of forest land in marwah forest division is recommendedYes
Nodal Officer RecommendedTo provide road connectivity.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Jammu and KashmirState SecretaryRecommended04/04/2022Recommended for grant of Stage I clearanceState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
JammuRegional Office9-JKC-019/2022-Jammu21/10/2022
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/JK/ROAD/51130/2020ROAD51130202058510,571,728.2010,571,729.0009/03/2023896112Union Bank Of IndiaNEFT/RTGS (Challan)NANA
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 12   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)12
  Status of CA Land so identified : Forest Area   Site Name : 38b/D Patimhalla Forest   Location Details : Patimhalla   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Patimhalla ForestRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/JK/ROAD/51130/202015 Mar 2023No Dataverified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/JK/ROAD/51130/202015 Mar 2023
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/JK/ROAD/51130/2020Recommended for stage-II approval 17 Feb 2025
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/JK/ROAD/51130/2020Approved In-PrincipleNo Data