PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
JK-018/2022
1.
Location of the project/Scheme :
Jammu and Kashmir
(i)
State / Union Territory :
Jammu and Kashmir
(ii)
District :
Kishtwar
(iii)
Forest Division :
Marwah Forest Division
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.028
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Marwah Forest Division
0.028
Reserved Forest
Total
0.028
Division 1. : Marwah Forest Division
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Kishtwar
0.028
Total
0.028
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.028
0.5
Eco 6
Total.
0.028
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Pine
Kail(Pinus wallichiana)
8
1
0
0
0
0
2
Others
hum(Fraxinus exclsior)
0
0
0
0
0
1
3
Others
HC Nut(Aesculus indica)
0
0
0
0
0
2
Total
8
1
0
0
0
3
Sub Total (No of Trees.)
12
5.
Working plan prescription for the forest land proposed for diversion :
Comptt. 70a/U is assigned to Deodar Kail irregular Working Circle.the Comptts. included in this working circle have gentle slope, adequate matured growing stock and can be managed under system of concentrated felling.
6.
Brief note on vulnerability of the forest area to erosion :
During rock cutting, some forest erosion is likely to occur as such user agency has assured to construct the retaining walls.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
monkeys, black bear, Langoor, Leaopard, jackal, fox etc.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
1.15037
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.60
Synthan Forest
Dachhan
80U
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
comments from Wildlife Warden Chenab Division Kishtwar
2
Reply of EDS
3
SOI Map 80/U
4
Reply of EDS as sought by IRO Jammu
5
Reply of EDS sought vide No. PCCF/FCA/3462/3376-78 Dt. 02.08.2022
6
CA Plan
7
Site Inspection Report (SIR)
8
Recommendation by DFO
9
Geo Reference Map 80U
10
CA Approval
11
Joint inspection
12
enumeration list
13
minimum use of forest land
14
NPV undertaking
15
CA undertaking
16
Checklist 17
17
NPV calculation
18
employment generation
19
general checklist
20
specific recommendation
21
SOI Map
22
time period certificate
23
checklist 7
24
checklist 20
25
Area Statement
26
component wise breakup
27
degraded forest land
28
GEO reference Map
29
undertaking regarding Muck disposal submitted by User Agency
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Kishtwar
773700
334006.91
528.2949
37
1926
23/03/2022
1926
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Marwah Forest Division
Chenab Circle Doda
DFO
Yes
One
08/03/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Marwah Forest Division
Chenab Circle Doda
DFO
Recommended
The construction of bridge over Synthan Nallaha of Watsar to Dangar Nallah road is essentially required for smooth vehicular movement and presently the said road is connected with culvert which is not suitable for vehicular movement.
Chenab Circle Doda
CF
Recommended
Forest land diversion under PMGSY Division Chatroo for construction of 40 MTR span motorable bridge over synthen nallah of watsar to dangar nallah road km 2nd RD 140 190 in marwah forest division is hereby recommended for approval under FCA. Total of 0.028 hac of forest land in marwah forest division is recommended.
Yes
Nodal Officer
Recommended
Recommended.
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Jammu and Kashmir
State Secretary
Recommended
25/05/2022
Recommended for grant of Stage I Clearance.
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Jammu
Regional Office
9-JKA-025/2022-Jammu
28/08/2022
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/JK/ROAD/151405/2022
ROAD1514052022066
153,465.00
153,465.00
05/01/2023
840536
Union Bank Of India
NEFT/RTGS (Challan)
26/12/2022
27/12/2022
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/JK/ROAD/151405/2022
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×