PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : JK-014/2020
1. Location of the project/Scheme : Jammu and Kashmir
 (i) State / Union Territory : Jammu and Kashmir  (ii) District : Anantnag  (iii) Forest Division : Anantnag Forest Division  (iv) Area of forest land proposed for diversion (in ha.) : 0.2  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Anantnag Forest Division0.2Reserved Forest
Total 0.2
Division 1. : Anantnag Forest Division
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Anantnag0.2
Total0.2
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.20.2Eco 6
Total. 0.2


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Pinus Griffithi MichellKail003876
Total 0 03 87 6
Sub Total (No of Trees.) 24


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : no threat of soil erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.05
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : No
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : This project is maintained for Tourist Facilitation Center & Security Cabin
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 318226
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.4ZesnardDaksum30/K    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Justification of Distance Certificate
2 Site suitability certificate of CA mentioning proposal CA Site
3 Compensation of Trees
4 Minimum use of Forest Land
5 Revised Site Inspection Report
6 Calculation/Evaluation of Net Present Value
7 Joint Inspection Report
8 Justification Certificate
9 Layout Plan Tourist Facilitation Cerntre
10 Muck Disposal Certificate
11 To Whom it may concern regarding Muck Certificate
12 Undertaking for payment of NPV and other Compunents
13 Abstract of Trees
14 Check List of KDA
15 Undertaking for cost of Compensatory Afforestration
16 Letter of Acceptance
17 Project Report of Extraction of Trees
18 Undertaking of cost of Compensatory Afforestration
19 Undertaking for Payment of NPV and Other components
20 Details of Forest Land Showing Dimensions
21 Enumeration List of Trees
22 Model Compensatory Afforestration Scheme

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Anantnag398400798633028725407/09/2020
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Anantnag Forest DivisionSouth Circle BijbeheraDFOYesOne04/05/2020
 South Circle BijbeheraCFNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Anantnag Forest DivisionSouth Circle BijbeheraDFO RecommendedThe Executive Officer Tourism Development Konernag has applied online for Diversion of Forest Land for Construction of Tourist Facilitation Center and Security Cabin at Daksum for processing the case for forest clearance a joint survey of the area has been conducted.
South Circle BijbeheraCF RecommendedFor promoting the facilitation to the tourists visiting the areas under Kokernag Development Authority, the construction of the Tourist facilitation center at Daksum will pave a way for boosting the tourism potential and traditional knowledge system in the tourism area. Yes
Nodal Officer Recommendedto promote the tourism activities in the area
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Jammu and KashmirState SecretaryRecommended18/11/2020 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
JammuRegional Office9-JKB004/2020-JAMMU11/05/2021
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/JK/Others/44473/2020OTHERS444732020611497,626.00497,626.0021/10/2021JAKA029300078081Union Bank Of IndiaNEFT/RTGS (Challan)13/10/202120/10/2021
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/JK/Others/44473/2020Approved In-PrincipleNo Data