PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : JK-042/2021
1. Location of the project/Scheme : Jammu and Kashmir
 (i) State / Union Territory : Jammu and Kashmir  (ii) District : Kathua  (iii) Forest Division : Basholi Forest Division  (iv) Area of forest land proposed for diversion (in ha.) : 0.36  (v)

Category of the Proposal: Hydel
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Basholi Forest Division0.36Reserved Forest
Total 0.36
Division 1. : Basholi Forest Division
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Kathua0.36
Total0.36
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.360.7Eco 5
Total. 0.36


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

(iii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-2 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

(iv) Species-wise local/scientific names and girth-wise enumeration of trees at FRL-4 meter
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL

5. Working plan prescription for the forest land proposed for diversion : Protection Working Circle
6. Brief note on vulnerability of the forest area to erosion : less prone to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Jungal Cat (Felis chaus), Indian Porcupine (Hustrix indica), Leopard Or Panther (Panthera pardus),
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 2.43
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
110.60Thathi-IIBasohli24/Bsl    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 C.A. Proposal
2 Geo-reference Map of CA Site
3 Suitability certificate
4 Calculation Sheet of NVP
5 Undertaking All
6 Muck Disposal Plan
7 Joint Inspection with User Agency
8 Check List DFO
9 Approval of the project by the Competent Authority
10 Site Inspection Report
11 Enumeration list
12 Calculation of Area
13 Layout plan with dimensions
14 Extraction Charges
15 Specific Recommendation
16 DPR of the Project
17 Minimum Land Required
18 Check list user Agency

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Kathua26510011097483.8117100931/03/202010090
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Basholi Forest DivisionEast Circle JammuDFOYesOne24/03/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Basholi Forest DivisionEast Circle JammuDFO RecommendedMay be accepted as per the guideline of GOI as the project is essential for the restoration of Sewa II Power Station, Mashka
East Circle JammuCF RecommendedThe case is recommendedYes
Nodal Officer RecommendedTo restore the power supply.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Jammu and KashmirState SecretaryRecommended05/05/2021 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
JammuState GovernmentFst/Land/Parivesh/61/202104/05/2021
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/JK/HYD/127255/2021HYD1272552021382395,145.00395,145.0001/06/2021SBIN221152392226Union Bank Of IndiaNEFT/RTGS (Challan)29/05/202131/05/2021
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 0.6   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)0.6
  Status of CA Land so identified : Forest Area   Site Name : Thathi-II   Location Details : 24/Bsl   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
NA
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/JK/HYD/127255/202119 Apr 2022No DataAccepted
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/JK/HYD/127255/202124 Jun 2022
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/JK/HYD/127255/2021Recommended for Stage-II approval14 Jul 2022
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/JK/HYD/127255/202116 Aug 2022APPROVED