Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
JK-078/2020
1.
Location of the project/Scheme :
Jammu and Kashmir
(i)
State / Union Territory :
Jammu and Kashmir
(ii)
District :
Baramula
(iii)
Forest Division :
Bandipora Forest Division
(iv)
Area of forest land proposed for diversion (in ha.) :
0.045
(v)
Category of the Proposal:
Approach Access
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Bandipora Forest Division
0.045
Reserved Forest
Total
0.045
Division 1. : Bandipora Forest Division
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Baramula
320000
Total
320000
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
1104.79
0.2
Eco 6
Total.
1104.79
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Pine
Kail/Kayer
5
0
1
0
0
0
2
Abies Alba
Fir/Budul
15
2
0
0
0
0
3
Acer Cambelli
Chad
1
0
0
0
0
0
Total
21
2
1
0
0
0
Sub Total (No of Trees.)
24
5.
Working plan prescription for the forest land proposed for diversion :
Un-regulated Working Plan
6.
Brief note on vulnerability of the forest area to erosion :
Prone to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
2
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
No
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
2.5
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.045
RF
Gurez
43/T
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
DPR
2
Site Suitability Certificate for CA
3
Joint Inspection Report(JIR)
4
Claculation Sheet of Extraction Charges
5
Calculation Sheet NPV
6
Letter of Acceptance
7
Site Inspection Report
8
Calculation Sheet of Area
9
Enumeration List of Trees
10
Check List
11
Lay Out Plan
12
Minimum Use Certificate
13
Undertaking to pay CA Cost
14
Technical Certificate
15
Undertaking to Pay Cost of NPV Etc
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Baramula
320000
199396
286.2788
29
572.5576
04/09/2020
572.5576
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Srinagar Circle
CF
No
No Data
Bandipora Forest Division
Srinagar Circle
DFO
Yes
One
28/07/2020
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Bandipora Forest Division
Srinagar Circle
DFO
Recommended
The construction of bridge in question is a critical development initiative for the local population of Gurez Valley and Security forces to connect from one place to another and to reach LOC. The construction of the bridge is a back bone to increase connectivity and cover gaps in all the villages of Gurez particularly Tulial Tehsil and get timely delivery of govt. initiatives/programmes.
Srinagar Circle
CF
Recommended
As it is essential to maintain the lifeline between Dawar and Tulail Dawar Neeru Buduaob Chakwali Koblgali Road in Gurez Region, it is not only essential to construct ‘60 metres single span major pmt bridge at Chak nallah’, from security point of view, but will also benefit the people of the area and strengthen the communication infrastructure. It is recommended that proposal may be approved.
Yes
Nodal Officer
Recommended
To provide road connectivity to the remote areas.
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Jammu and Kashmir
State Secretary
Recommended
17/03/2021
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Jammu
State Government
Fst/Land/Parivesh/38/2020
17/03/2021
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/JK/Approach/44582/2020
APPROACH445822020860
281,455.00
281,455.00
20/05/2021
SBIN513925278695
Union Bank Of India
NEFT/RTGS (Challan)
05/04/2021
17/04/2021
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/JK/Approach/44582/2020
IN-PRINCIPLE
No Data
Print
Checklist for State Nodal Officer
×