PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
JH-023/2022
1.
Location of the project/Scheme :
Jharkhand
(i)
State / Union Territory :
Jharkhand
(ii)
District :
Bokaro
(iii)
Forest Division :
Bokaro
 (iv)
Area of forest land proposed for diversion (in ha.) :
8.3618
 (v)
Category of the Proposal:
Pipeline
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Bokaro
0.2818
Protected Forest
2
Bokaro
8.08
jungle-jhari land
Total
8.3618
Division 1. : Bokaro
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Bokaro
8.3618
Total
8.3618
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
8.3618
0.5
Eco 3
Total.
8.3618
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Butea Monosperma
Palash
754
204
146
48
16
6
2
Tamarindus Indica
Imli
0
0
0
0
0
1
3
Others
Jungle Tree
2
4
4
0
0
0
4
Bamboo
Bamboo
19
0
0
0
0
0
5
Others
Sindhvar
24
6
5
1
0
0
6
Others
Sahada
4
5
4
0
0
0
7
Sal
Sal
2
0
0
0
0
2
8
Albezzia Labbeck
Shirish
1
5
2
1
0
0
9
Azadirachta Indica
Neem
5
1
2
1
0
1
10
Madhuka Indica
Mahua
0
1
0
0
1
1
11
Others
Papaya
1
0
0
0
0
0
12
Ficus Racemosa
Dumar
0
0
1
0
0
0
13
Bombax Ceiba
Simal
0
1
1
1
1
0
14
Emblica Officianalis
Amla
1
0
0
0
0
0
15
Karanj
Karanj
1
0
0
0
1
1
16
Syzigium Cumini
Jamun
0
0
0
1
0
0
17
Terminalia Bellarica
Bahera
0
0
0
0
0
1
18
Others
Raipan
32
0
0
0
0
0
19
Diasporus Melanoxylon
Kendu
0
0
0
0
0
1
20
Psidium Guajava
Amrud
0
1
0
0
0
0
21
Zizyphus Jujuba
Bair
0
1
1
0
0
0
22
Others
Rifal
7
0
0
0
0
0
23
Others
Leptis
87
0
0
0
0
0
24
Cassia Siamea
Chakundi
21
0
0
0
0
0
Total
961
229
166
53
19
14
Sub Total (No of Trees.)
1442
5.
Working plan prescription for the forest land proposed for diversion :
Proposed area for diversion comes under Rehabilitation Cum Plantation Working Circle.
6.
Brief note on vulnerability of the forest area to erosion :
Area is prone to soil erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Hyena, Snake, Jackal etc.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
61.13073
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
16.73
Raghunathpur
Peterwar
Plot no. 17, 41, 441
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Offline Part-II
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Bokaro
286100
54393
1672.069
38
3802.71
30/09/2022
5279.04
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Bokaro
Bokaro
DFO
Yes
One
15/09/2022
Bokaro
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Bokaro
Bokaro
DFO
Recommended
This project will connect ONGC Bokaro to JHBDPL Jagdishpur Haldia Bokaro Dhamra Pipe Line network of GAIL by pipeline. Hence the proposal for diversion is recommended in national interest and may be accepted for diversion as per provisions of FC Act.
Bokaro
CF
Recommended
As the project is site specific and in public interest, it is recommended.
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Jharkhand
State Secretary
Recommended
13/03/2023
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Ranchi
Regional Office
FP/JH/Pipeline/152290/2022
27/04/2023
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/JH/Pipeline/152290/2022
PIPELINE1522902022281
17,671,934.00
17,671,934.00
12/05/2023
946728
Union Bank Of India
NEFT/RTGS (Challan)
11/05/2023
12/05/2023
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
16.73
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
16.73
Status of CA Land so identified :
Forest Area
Site Name :
District: Bokaro Range: Peterwar Village: Raghunathpur Thana: Kasmar Thana No.: 106 Plot No.: 17, 41, 441 Forest Diversion Area: 8.3618 Ha. (Bokaro Division) CA Land Area: 16.73
Location Details :
N 23°33'17.5", E 85°54'2.03"
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Notified Forest land
PF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/JH/Pipeline/152290/2022
04 Jul 2023
No Data
Verified
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/JH/Pipeline/152290/2022
04 Jul 2023
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/JH/Pipeline/152290/2022
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×