PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : JH-046/2019
1. Location of the project/Scheme : Jharkhand
 (i) State / Union Territory : Jharkhand  (ii) District : Ramgarh,Hazaribag  (iii) Forest Division : Ramgarh,Hazaribagh West  (iv) Area of forest land proposed for diversion (in ha.) : 11.11  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Ramgarh2.84jungle-jhari land
2Hazaribagh West4.68Protected Forest
3Hazaribagh West3.59jungle-jhari land
Total 11.11
Division 1. : Hazaribagh West
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Hazaribag8.27
Total8.27
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
18.270.2Eco 3
Total. 8.27


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : Working plan prescription for the forest land proposed for diversion in Rehabilitation and plantation cum-soil conservation working circle as the area in totally blank so only plantation and soil conservation works proposed.
6. Brief note on vulnerability of the forest area to erosion : Proposed Forest Area is vulnerable to soil erosion and in some part gully erosion is also present inside the forest area proposed for the diversion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Vulture, Hyena, Python, Nilgai, Wild Boar, Spotted Deer, Fox, Indian Cobra, Jungle Cat, Jackal, Peacock, Chameleon, Rabbit etc. are present in and around proposed forest land.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 67.14680
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1117ChhiramoBarhi409P    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Undertakings, FRA and LandSchedule- Hazaribag West Forest Division
2 Part -II of North Urimari- Hazaribag West Forest Division
Division 2. : Ramgarh
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Ramgarh2.84
Total2.84
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
12.840.3Eco 3
Total. 2.84


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Azadirachta IndicaNeem174000
2Lagerstroemia ParvifloraSidha041000
3Tectona GrandisSagwan010000
4Gmelin ArboreaGamhar3111000
5Cassia SiameaChakundi013472340
6Mangifera IndicaAam130000
7Butea MonospermaPalash001000
8Misc. SpeciesJangli, amda200000
Total 7 3954 234 0
Sub Total (No of Trees.) 127


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The area is moderately prone to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Rabbit, wild boar, Snakes, Jackal etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : Yes
  (a)Details of violation(s): Work started in GMJJ Land
   (b) Period of Work done(year) : 0.5
   (c) Area of forest land involved in violation (in ha.) : 2.84
S. No. Name of person responsible for violation Designation & Address of person responsible for violationAction taken against the person responsible for violation
1CCLGMJJ Land
12. Whether work in violation is still in progres(Yes/No) : No
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 33.95642
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
115.90ChainpurMandu810    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 FRA and Gram Sabha of North Urimari-Ramgarh Forest Division
2 Part -II of North Urimari- Ramgarh Forest Division

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Hazaribag4302002038003794.237266482.393231/03/20215365.370
2Ramgarh136008487933508.66524811.2608/09/20214811.260
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
RamgarhBokaroDFOYesOne16.06.2021
Hazaribagh WestHazaribaghDFOYesOne02/03/2021
 BokaroCFNoNo Data
 HazaribaghCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Hazaribagh WestHazaribaghDFO RecommendedThe proposed site of Forest Diversion of CCL Railway siding at North Urimari Railway siding was inspected on 2nd. March, 2021 measuring an area of 11.11 ha. H.bag West 8.27ha. . in the corresponding villages Urimari in Barkagaon Range.
RamgarhBokaroDFO RecommendedThe North Urimari Railway Siding 2.84 ha for dispatch of coal produce from Urimari OCP Project Project, proposal is recommended for diversion as per the provision of FC Act/Rule
BokaroCF RecommendedThe North Urimari Railway Siding 2.84 ha. proposal is recommended.Yes
HazaribaghCF RecommendedThe Proposed site of Forest Diversion of CCL North Urimari Railway siding measuring an area 8.27 ha. Notified forest 4.68 ha. & Jungle Jhari forest 3.59 ha. in Hazaribagh West Forest Division is recommended as per the provision of Forest Conservation Act, 1980 in national interest with adequate soil conservation measure in adjoining areas.Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
JharkhandState SecretaryRecommended03/01/2023RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
RanchiRegional OfficeFP/JH/others/34881/201812/07/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/JH/Others/34881/2018OTHERS348812018550100,662,869.80100,662,870.002023-07-2853938Union Bank Of IndiaNEFT/RTGS (Challan)NANA
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 111.1   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)111.1
  Status of CA Land so identified : Forest Area   Site Name : Dumuhani Neematand   Location Details : Barkattha, Barhi Range   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Other Forest Land
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/JH/Others/34881/201805 Oct 2023No DataVerified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/JH/Others/34881/201809 Oct 2023
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/JH/Others/34881/2018Stage I Compliance02 Nov 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/JH/Others/34881/2018Approved In-PrincipleNo Data