PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : JH-039/2016
1. Location of the project/Scheme : Jharkhand
 (i) State / Union Territory : Jharkhand  (ii) District : Bokaro  (iii) Forest Division : Bokaro  (iv) Area of forest land proposed for diversion (in ha.) : 68.4  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Bokaro65.9Protected Forest
2Bokaro2.5jungle-jhari land
Total 68.4
Division 1. : Bokaro
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Bokaro68.4
Total68.4
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
168.40.7Eco 3
Total. 68.4


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Terminalia TomentosaAsan0459482230
2Abies AlbaAnjan001000
3Abies AlbaArmo08732300
4Terminalia BellaricaBahera081000
5Abies AlbaBandarloya070000
6Abies AlbaBanderlor050000
7Abies AlbaBarka Konar005100
8Abies AlbaBehra031000
9Aegle MarmelosBel054922200
10Abies AlbaBhalu Sua010000
11Semecarpus AnacardiumBhelwa015320520
12Holoptelia integrifoliaBhurkund (Hymenodictyon excelsum)0111000
13Abies AlbaChailli02813000
14Abies AlbaChaproy031000
15Cassia SiameaChakundi054000
16Abies AlbaDhatwa0111000
17Abies AlbaDoka04851933450
18Ficus BengalensisDumar (Ficus Glomerata)04317410
19Couroupita GuianensisGalgal (Cocholospermum religiosum)011543600
20Abies AlbaHupu000100
21Syzigium CuminiJamun0657110
22Casurina EquisitifoliaJungli Ber020236130
23Adina cordifoliaKaram06325820
24Abies AlbaKarkar001000
25Abies AlbaKasmar021000
26Diasporus MelanoxylonKend052031420
27Acacia CatechuKhair060000
28Abies AlbaKhar070000
29Abies AlbaKhat001000
30Acacia CatechuKhayar010000
31Abies AlbaKher030000
32Abies AlbaKurei0161000
33Abies AlbaKusum (Schleichera oleosa)06416110
34Madhuca indicaMahuwa0232080
35Abies AlbaMunga050000
36Azadirachta IndicaNeem0124000
37Acacia ArabicaPaisar031000
38Abies AlbaPapari0101000
39Butea MonospermaParas092401110
40Abies AlbaPiranji0122471320
41Ficus ReligiosaPipal069010
42Abies AlbaPiyar0299518848120
43Butea MonospermaPlas07631790
44Abies AlbaPutar08826000
45Abies AlbaRaram000000
46Abies AlbaRaypan0682573000
47Abies AlbaRoli003000
48Abies AlbaSakhua02293345116160
49Abies AlbaSaram020000
50Lagerstroemia ParvifloraSidha035472611150
51Abies AlbaSimar011100
52Albezzia LabbeckSiris08417200
53Dalburgia SisooSisam061000
54Abies AlbaV. Prajati0268734786200
Total 0 156561903 41894 0
Sub Total (No of Trees.) 18071


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The proposed area is hilly terrain, so the area is prone to soil erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Hyaena, Rock Python, Peacock, Jungle Quail, Indian Jackal, Russel Viper etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 343.63296
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1150NasiaBokaroNA    View file
2240JunodihBokaroNA    View file
3350TaratandBokaroNA    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Bokaro286100543931336.874293533.3005/10/20162780.060
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
BokaroBokaroDFOYesOne08/08/2016
 BokaroCFYesOne07/10/2016
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
BokaroBokaroDFO Recommended
BokaroCF RecommendedYes
Nodal Officer Recommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
JharkhandState SecretaryRecommended30/05/2017 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
RanchiHead Office8-42/2017-FC22/06/2018
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/JH/Others/20067/2016OTHERS20067201657619,987,673.0019,987,673.002019-08-19SBINR52019081900130619Corporation BankNEFT/RTGS (Challan)2019-05-032019-05-08
FP/JH/Others/20067/2016OTHERS20067201626554,576,500.0054,576,500.002023-05-29965447Union Bank Of IndiaNEFT/RTGS (Challan)2023-05-122023-05-16
FP/JH/Others/20067/2016OTHERS20067201665423,443,884.0023,443,900.002024-01-16ICICR22024011601408220Union Bank Of IndiaNEFT/RTGS (Challan)NANA
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/JH/Others/20067/2016Approved In-PrincipleNo Data