PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
HR-0132/2022
1.
Location of the project/Scheme :
Haryana
(i)
State / Union Territory :
Haryana
(ii)
District :
Sirsa
(iii)
Forest Division :
Sirsa
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.09558
 (v)
Category of the Proposal:
Transmission Line
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Sirsa
0.09558
Protected Forest
Total
0.09558
Division 1. : Sirsa
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Sirsa
0.09558
Total
0.09558
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.096
0.4
Eco 3
Total.
0.096
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Dalburgia Sisoo
SHISHM
1
3
1
0
0
0
2
Acacia Nilotica
KIKAR
0
0
0
0
0
1
3
Eucalyptus
SAFEDA
0
2
3
4
1
1
4
Misc. Species
MISC. SPECIES
0
1
2
0
0
0
Total
1
6
6
4
1
2
Sub Total (No of Trees.)
20
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
Not prone to erosion
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Local Wildlife.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
605750
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
0.234
Ottu Feeder RD 55-65 Righr side
Rania
Nil
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
Part II
2
NPV Sheet
3
Forwarding Letter Against 9-HRB128/2022-CHA on dated 19-07-2023
4
NOC PWD
5
CL 8
6
Request Letter by User Agency
7
Site Inspection Report CL 16
8
Undertaking Additional NPV
9
Forwarding Letter
10
NOC Irrigation
11
CL 17
12
Land Suitability Certificate CL 20
13
Authority Letter of User Agency
14
Check List
15
CL 10
16
CL 11
17
CL 12
18
CL 13
19
Part I to V
20
Works Detail of Proposal submitted by User Agency
21
CA Toposheet
22
CA Scheme
23
Approved Layout Plan
24
CL 7
25
Check List 16
26
Check List 20
27
CHECK LIST
28
Marking List
29
CA DGPS
30
Forwarding Letter Against 9-HRB128/2022-CHA on dated 03-03-2023
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Sirsa
484600
4804.81
275.49755
310
489.91882
30/09/2021
437.2904
2.00
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Sirsa
West Circle Hissar
DFO
Yes
One
20/01/2022
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Sirsa
West Circle Hissar
DFO
Recommended
Recommended in Public Interest
West Circle Hissar
CF
Recommended
Recommended
Yes
Nodal Officer
Recommended
Recommendation
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Haryana
State Secretary
Recommended
06/06/2022
Recommendation
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Chandigarh
Regional Office
9-HRB128-2022-CHA
13/10/2023
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/HR/TRANS/148304/2021
TRANS1483042021480
605,750.00
605,750.00
2023-11-03
SBINR52023113086834653
Union Bank Of India
NEFT/RTGS (Challan)
2023-10-18
2023-11-09
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/HR/TRANS/148304/2021
13 Feb 2024
No Data
NA
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/HR/TRANS/148304/2021
27 Feb 2024
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/HR/TRANS/148304/2021
Compliance sent to SG
11 Mar 2024
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/HR/TRANS/148304/2021
14 Apr 2024
APPROVED
Print
Checklist for State Nodal Officer
×