PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : HR-063/2020
1. Location of the project/Scheme : Haryana
 (i) State / Union Territory : Haryana  (ii) District : Faridabad  (iii) Forest Division : Faridabad  (iv) Area of forest land proposed for diversion (in ha.) : 9.08  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Faridabad9.08Protected Forest
Total 9.08
Division 1. : Faridabad
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Faridabad9.08
Total9.08
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
19.080.6Eco 1
Total. 9.08


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Eucalyptussafeda01418932322847
2Dalburgia Sisooshisham02728261817
3Acacia Niloticakikar04181073
4Othersothers02512351498386
Total 0 296470 508336 153
Sub Total (No of Trees.) 1763


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : nil
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : nil
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 51566523.35
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
119.08Chhaainsa distyBallabhgarhchhainsa Disty    View file
229.08Dhoj BUndhBallabhgarhDhoj BUndh    View file
339.08Gounchi Main DrainBallabhgarhGounchi Main Drain    View file
449.08Harchandpur DistryBallabhgarhHarchand pur Disty    View file
559.08Kot BundhBallabhgarhKot BUndh    View file
669.08Rampura DistributryBallabhgarhRampura Distributry    View file
779.08Sikrona MinorBallabhgarhSikrona MInor    View file
889.08kot section 4&5Ballabhgarhkot section 4&5    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1
2
3
4
5 marking list
6
7

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Faridabad210500460532812344.5001/01/2018264.320
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
FaridabadSouth Circle GurgaonDFOYesOne08/06/2020
 South Circle GurgaonCFYesOne28/10/2020
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
FaridabadSouth Circle GurgaonDFO RecommendedA the proposal is for widening of road and there is very rush on this road and in public intrest it is recommended
South Circle GurgaonCF RecommendedRecommended.Yes
Nodal Officer RecommendedRecommended for approval
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
HaryanaState SecretaryRecommended12/02/2021 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhRegional Office9-HRC031-2021-CHA29/04/2021
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/HR/ROAD/43612/2019ROAD43612201905351,566,523.3551,566,523.352021-12-27HDFC236086213242Union Bank Of IndiaNEFT/RTGS (Challan)2021-12-222021-12-22
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/HR/ROAD/43612/201922 Mar 2022No DataNA
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/HR/ROAD/43612/2019Approved In-PrincipleNo Data