PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : HR-0422/2016
1. Location of the project/Scheme : Haryana
 (i) State / Union Territory : Haryana  (ii) District : Karnal  (iii) Forest Division : Karnal  (iv) Area of forest land proposed for diversion (in ha.) : 0.94  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Karnal0.94Protected Forest
Total 0.94
Division 1. : Karnal
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Karnal0.94
Total0.94
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.940.6Eco 2
Total. 0.94


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersShisham,Kikar,Misc062541236
Total 0 625 412 36
Sub Total (No of Trees.) 110


5. Working plan prescription for the forest land proposed for diversion : Na
6. Brief note on vulnerability of the forest area to erosion : NA
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Na
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 27.81
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
111.88R.F SHEIKHUPURA KarnalR.F SHEIKHUPURA    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 FRA Attached

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Karnal3721762.21579.41519625323/01/20172531.56
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
KarnalCentral Circle RohtakDFOYesOne19/01/2017
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
KarnalCentral Circle RohtakDFO RecommendedThe project is recommended for acceptance as there is no other alternative for Construction of 45 Mtr. Wide road behind sector-8, Part-II and sector-9 U.E under Division & Distt. Karnal(Haryana).& minimum Forest land required by the user is 0.94 hectare
Central Circle RohtakCF RecommendedYes
Nodal Officer RecommendedRecommended for Approval
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
HaryanaState SecretaryRecommended20/02/2017Recommended for Approval State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ChandigarhRegional Office9-HRB040-2017-CHA18/04/2018
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/HR/ROAD/21601/2016ROAD2160120168942,023,982.002,023,982.002018-06-08PUNBH18159150187Corporation BankNEFT/RTGS (Challan)2018-05-172018-05-18
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 0.94   (iii). No. of Maintenance years: 100   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)0.94
  Status of CA Land so identified : Non Forest Area   Site Name : Behind sector 9 along road green belt   Location Details : Behind sector 9 along road green belt   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
Central Circle RohtakKarnalKarnal224805 Dec 20190.94
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/HR/ROAD/21601/201614 Jan 2020No DataNA
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/HR/ROAD/21601/201617 Jan 2020EDS: upload the information21 Jun 2021
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/HR/ROAD/21601/201604 Mar 2020
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/HR/ROAD/21601/2016Approved In-PrincipleNo Data