PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : HP-0172/2022
1. Location of the project/Scheme : Himachal Pradesh
 (i) State / Union Territory : Himachal Pradesh  (ii) District : Shimla  (iii) Forest Division : Rampur  (iv) Area of forest land proposed for diversion (in ha.) : 3.2193  (v)

Category of the Proposal: Road
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Rampur2.7513Unclassed Forests
2Rampur0.468Protected Forest
Total 3.2193
Division 1. : Rampur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Shimla3.2193
Total3.2193
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
13.21930.04Eco 6
Total. 3.2193


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersDeodar (Cedrus deodara)013000
2OthersKail (Pinus wallichiana)16176100
3OthersRai (Picea smithiana)000100
4OthersBan (Quercus leucotricophora)041000
5OthersChil (Pinus roxburghii)1472000
Total 30 2912 20 0
Sub Total (No of Trees.) 73


5. Working plan prescription for the forest land proposed for diversion : The area falls under Deo/Kail PB-III circle
6. Brief note on vulnerability of the forest area to erosion : The area is not seriously eroded or is not much vulnerable to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.00
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Wolf (Canis pallips), India Fox (Vulpes bengalensis), Indian porcupine (Hystrix indica), Brown flying squirrel (Peeromys petaurista), Monkey (Macac malatta), Jackal (Canis aureus), Hill mouse (Mos homourus)
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : Yes
  (a)Details of violation(s): The user agency has violated the provisions of FCA
   (b) Period of Work done(year) : 2006
   (c) Area of forest land involved in violation (in ha.) : 3.0063
S. No. Name of person responsible for violation Designation & Address of person responsible for violationAction taken against the person responsible for violation
1XEN HPPWD RampurExecutive Engineer HPPWD Rampur BushahrThe committee constituted vide judgement of the Honble High Court of Himachal Pradesh
12. Whether work in violation is still in progres(Yes/No) : No
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 1173722
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
116.4386D-18 (Punan) C-4NankhariD-18 (Punan) C-4    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Bill of NPV
2 Certificate of no plantation has been done
3 Certificate of no trees standing
4 Detail of Private land
5 Certificate for minimum use of forest land
6 Undertaking regarding CA
7 Site inspection report
8 Details of non-forest land/degraded forest area identified for CA
9 Detailed CA & Penal CA Scheme
10 Joint inspection report
11 Map of the project site
12 Panalty bill of NPV
13 Plantation scheme for muck lumping
14 Revised Part-II
15 Land suitability certificate by DFO
16 Undertaking
17 Undertaking for possibility to shift the dumping site
18 Undertaking regarding NPV & addl. NPV
19 Justification
20 Check list 19
21 Detail of forest land
22 DGPS map of proposed road
23 Certificate W.L. Sanctuary
24 Bill of Penal NPV
25 Cost of trees

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Shimla12984839420.92779.21311011603.019231/03/20221715.57980
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
RampurRampurDFOYesOne20/06/2022
 RampurCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
RampurRampurDFO RecommendedThe case is recommended for approval please
RampurCF RecommendedJustification as per the check list No.10 is placed in the proposal folders.Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Himachal PradeshState SecretaryRecommended01/09/2023RecommendedState Govt. OfficerNo Data