PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : HP-0136/2015
1. Location of the project/Scheme : Himachal Pradesh
 (i) State / Union Territory : Himachal Pradesh  (ii) District : Kangra  (iii) Forest Division : Palampur  (iv) Area of forest land proposed for diversion (in ha.) : 0.9925  (v)

Category of the Proposal: Others
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Palampur0.9925Protected Forest
Total 0.9925
Division 1. : Palampur
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Kangra0.9925
Total0.9925
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.99250Eco 5
Total. 0.9925


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersNil000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : The proposed area falls in P9 P Bir C-V. This forest is under Ban Oak working circle. The working plan prescription in respect of Ban oak Working Circle has been uploaded as additional document.
6. Brief note on vulnerability of the forest area to erosion : There is no possiblilty of land erosion being strata
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Wild Boar, Porcupine, Sambhar, Terrestrial birds, hare etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 7.65757
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
12UP131B Baggidhar C-6BaijnathUP131B Baggidhar C-6    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 Complete Folder from page 1 to 28
2 Working Plan DA Area
3 Under taking regarding the complete proceeding with all annexures of the FRA certificate in respect of 0.9925 ha. of forest land will be submitted before seeking the final approval,stage-II.
4 Topo Map
5 Complete Folder from P 29 to 56
6 Site Inspection Report
7 NPV Bill
8 Special Recommendation
9 Revised Part II

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Kangra57390038817.3794.817147154.5431/03/2024154.540
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
PalampurD/SalaDFOYesOne29/08/2015
 D/SalaCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
PalampurD/SalaDFO Recommended
D/SalaCF RecommendedYes
Nodal Officer Recommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
Himachal PradeshState SecretaryRecommended12/07/2017 Recommended State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
ShimlaRegional Office8B/HP/09/90/201722/01/2025
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/HP/Others/14799/2015OTHERS1479920159521,680,704.001,680,700.0018/07/2025PUNBR52025071814705164Union Bank Of IndiaNEFT/RTGS (Challan)28/01/202530/01/2025
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/HP/Others/14799/201528 Oct 2025No DataCA has been proposed over degraded Forest land, hence mutation is not required.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/HP/Others/14799/201503 Dec 2025
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/HP/Others/14799/2015Compliance report20 Dec 2025
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/HP/Others/14799/201509 Jan 2026APPROVED