PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
HP-0118/2019
1.
Location of the project/Scheme :
Himachal Pradesh
(i)
State / Union Territory :
Himachal Pradesh
(ii)
District :
Kullu
(iii)
Forest Division :
Ani at Luhri
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.9486
 (v)
Category of the Proposal:
Hydel
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Ani at Luhri
0.9486
Protected Forest
Total
0.9486
Division 1. : Ani at Luhri
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Kullu
0.9486
Total
0.9486
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.9486
0.3
Eco 5
Total.
0.9486
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Melotus Philippensis
Reuin
5
0
0
0
0
0
2
Dalburgia Sisoo
Shisham
92
1
0
0
0
0
3
Others
Kakar Singhi (Pistacia integerrima)
1
0
0
0
0
0
Total
98
1
0
0
0
0
Sub Total (No of Trees.)
99
(iii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL-2 meter
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
(iv)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL-4 meter
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
The working plan of this division has been expired on 31.03.2015.However as per old working of Outer seraj the proposed area falls under improvement working circle.
6.
Brief note on vulnerability of the forest area to erosion :
Not vulnerable
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.50
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Leopard, Fox, Bear, Ghoral etc.
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
454280
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
1.89
1-19 Lamidhar
Chowai
1/19
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
1
location map
2
Digital map of Proposed cite
3
Bill of NPV
4
Cost Norm of CA scheme
5
Joint Inspection Report
6
Toposheet of Proposed site
7
Bill scheme of CA area
8
Justification of land
9
Bill of Trees
10
detail of trees
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Kullu
71500
53502.36
436.8889
93
754.497
31/01/2019
575.744
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Ani at Luhri
Rampur
DFO
Yes
One
22/10/2019
Rampur
CF
No
No Data
Nodal Officer
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Ani at Luhri
Rampur
DFO
Recommended
Since the land in question is required for public development works, hence recommended for the purposed as proposed for by the User agency.
Rampur
CF
Recommended
The case is recommend for approval as per the justification given by the User Agency .
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Himachal Pradesh
State Secretary
Recommended
18/05/2020
Recommended
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Shimla
Head Office
8-48/2018-FC Vol.
21/12/2020
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/HP/HYD/39709/2019
HYD397092019543
1,028,126.00
1,028,126.00
2021-02-01
PUNB203118182473
Corporation Bank
NEFT/RTGS (Challan)
2021-01-23
2021-01-30
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
(i). Whether CA Land is mandatorily required in this Proposal :
Yes
(ii). Total Land identified for raising CA:
1.9
(iii). No. of Maintenance years:
10
(iv). Total No. of Patches/Parcel:
1
No. of patches :
1
Patch wise details
Patch No.
Shape of land identified for CA
Area of Patch/Parcel(in ha.)
1
Block(Polygon)
1.9
Status of CA Land so identified :
Forest Area
Site Name :
DPF 1-19 Lamidhar
Location Details :
Survey No./Compartment No. H43F7 near Village Lamidhar Tehsil Ani District Kullu
Uploaded GPS File :
Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest.
Legal Status of Forest Land
Degraded Forest
PF
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/HP/HYD/39709/2019
06 Feb 2021
No Data
CA has been proposed over degraded forest land, hence mutation is not required.
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/HP/HYD/39709/2019
16 Sep 2021
Compliance Details Submitted by User Agency(old)
Proposal No.
Compliance Details submitted on(Date)
Reject Remarks
Reject Date
Uploaded Letter
FP/HP/HYD/39709/2019
13 Aug 2021
EDS: EDS
08 Sep 2021
FP/HP/HYD/39709/2019
05 Aug 2021
EDS: Upload complete FRA certificate against column No. K i in part I
12 Aug 2021
FP/HP/HYD/39709/2019
06 Feb 2021
EDS: EDS
25 Mar 2021
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/HP/HYD/39709/2019
Compliance reported to GoI
02 Mar 2021
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/HP/HYD/39709/2019
13 Oct 2021
APPROVED
Print
Checklist for State Nodal Officer
×