PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : GJ-0187/2018
1. Location of the project/Scheme : Gujarat
 (i) State / Union Territory : Gujarat  (ii) District : Junagarh  (iii) Forest Division : Gir-West WL  (iv) Area of forest land proposed for diversion (in ha.) : 0.0588  (v)

Category of the Proposal: Village Electricity
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Gir-West WL0.0588Reserved Forest
Total 0.0588
Division 1. : Gir-West WL
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Junagarh0.0588
Total0.0588
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.05880Eco 3
Total. 0.0588


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
NIL
5. Working plan prescription for the forest land proposed for diversion : No Data
6. Brief note on vulnerability of the forest area to erosion : This Project is Required for electrification of new agriculture purpose
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Lion,Leopard,Deer etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : This Project is Required for electrification of new agriculture purpose
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 563600
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
111.00RFTalala0    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Junagarh88480018072238.47904227.476828/09/201868.476852.85
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
 Junagadh WL CircleCFNoNo Data
Gir-West WLJunagadh WL CircleDFOYesOne12/09/2018
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Gir-West WLJunagadh WL CircleDFO RecommendedRECOMMENDED
Junagadh WL CircleCF Recommended RecommendedYes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
GujaratState SecretaryRecommended09/09/2019 State Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
GandhinagarRegional Office6-GJB040/2019-BHO28/07/2020
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/GJ/VELEC/14450/2015VELEC144502015980618,000.00118,000.002022-08-25701816Union Bank Of IndiaNEFT/RTGS (Challan)2022-08-172022-08-20
FP/GJ/VELEC/14450/2015VELEC144502015980618,000.00500,000.002022-08-25701782Union Bank Of IndiaNEFT/RTGS (Challan)2022-08-172022-08-20
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) : No
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/GJ/VELEC/14450/201516 Sep 2022No Dataok
Compliance Details Submitted by User Agency(old)
Proposal No.Compliance Details submitted on(Date)Reject RemarksReject DateUploaded Letter
FP/GJ/VELEC/14450/201516 Sep 2022EDS: Reply as per GoI query.26 Apr 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/GJ/VELEC/14450/2015As per the letter02 May 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/GJ/VELEC/14450/2015Approved In-PrincipleNo Data