PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
GJ-0277/2019
1.
Location of the project/Scheme :
Gujarat
(i)
State / Union Territory :
Gujarat
(ii)
District :
Valsad
(iii)
Forest Division :
Valsad-South
 (iv)
Area of forest land proposed for diversion (in ha.) :
21.636
 (v)
Category of the Proposal:
Transmission Line
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Valsad-South
21.636
Reserved Forest
Total
21.636
Division 1. : Valsad-South
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Valsad
21.636
Total
21.636
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
21.636
60
Eco 4
Total.
21.636
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Butea Monosperma
khakharo
0
2
0
3
1
0
2
Others
payar
0
1
4
1
0
4
3
Others
Gundi
0
0
1
0
0
0
4
Others
Kusum
0
0
0
5
2
0
5
Others
Kumbh
0
0
0
2
3
7
6
Others
Sadad
0
13
47
60
18
8
7
Ficus Tomentosa
Umaro
0
0
0
1
2
2
8
Others
Alav
0
0
0
4
2
1
9
Azadirachta Indica
Limado
0
0
0
0
1
0
10
Tectona Grandis
Sag
0
22
14
4
1
4
11
Cassia Fistula
Garamalo
0
0
0
1
0
0
12
Others
Kalam
0
0
0
12
4
5
13
Tamarindus Indica
Aamali
0
0
0
0
0
3
14
Others
Kadayo
0
0
1
0
0
0
15
Others
Mahudo
0
0
4
5
9
13
16
Mangifera Indica
Pipalo
0
0
0
0
0
1
17
Others
Kher
0
1
1
0
0
0
18
Others
Kaju
0
2
4
6
3
0
19
Others
aachitro
0
0
3
1
2
0
20
Others
Behado
0
0
0
6
2
7
21
Others
Asan
0
1
10
10
3
2
22
Others
Hed
0
0
0
2
3
1
23
Others
Kadavai
0
1
1
0
1
0
24
Others
Dhamudo
0
0
4
6
9
3
25
Others
Tanas
0
0
0
1
0
2
26
Others
Papado
0
0
1
2
0
2
27
Others
Bodaro
0
0
2
3
2
2
28
Others
Simalo
0
0
0
3
1
1
29
Others
Karaval
0
0
0
0
0
1
30
Others
Kundi
0
0
0
1
0
0
31
Others
Davala
0
0
0
1
0
0
32
Others
Timaru
0
0
1
0
2
0
33
Others
Aasad
0
0
0
0
0
1
34
Others
Nimbaro
0
0
1
1
0
0
35
Others
Chamol
0
0
1
0
0
0
36
Others
Chameli
0
0
0
0
0
1
37
Others
Varas
0
0
0
2
0
0
38
Others
Madhal
0
0
0
0
1
0
39
Others
Aasitro
0
0
1
0
0
0
40
Others
Kilai
0
0
1
0
2
0
41
Others
Haladu
0
0
0
3
4
1
42
Others
Kharot
0
0
1
0
0
0
43
Others
Aalai
0
0
0
1
0
0
44
Others
Karanj
0
1
0
0
0
0
45
Others
Nilagiri
0
0
0
0
3
1
46
Others
Bili
0
1
0
0
0
0
47
Others
Boradi
0
0
1
0
0
0
48
Others
Itar
0
29
59
39
9
2
Total
0
74
163
186
90
75
Sub Total (No of Trees.)
588
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
Submission of 21.6360 Hac. Forest Land praposal for Diversion for forest land praposal for forest clearance for 66 kv Lilo Line for 66 kv Jiraval ,Nandgam,Ghanveri&Astol sub-statio
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
NO
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
22220000
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
1
1
44.00
RF
Vansda East
68
View file
(ii).
Copy of CA scheme details:
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority :
Additional information Details
S. No.
Documents
Remarks
NIL
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Valsad
330283
54962.56
2836.678
14
0
16/04/2020
0
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Valsad-South
Valsad Circle
DFO
Yes
One
08/04/2020
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Valsad-South
Valsad Circle
DFO
Recommended
Certified that all other alternative for the purpose have been explored and the demand for required area is the minimum demanded for forest land. it is recommended to divert this land for 66kv Lilo Line for 66kv Jirval sub station 2.1690 ha. & 66kv lilo line for 66kv Nandgam sub station 7.137 ha. and 66kv Astol Ghanvery line 12.330 ha. with Dog Conductor on D/C Panther Tower line to fed 66kv Jirval,Nandgam and Ghanveri Sub station.
Valsad Circle
CF
Recommended
Recommended
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Gujarat
State Secretary
Recommended
17/12/2021
Inprinciple Stage 1 approval will be issued by IRO Gandhinagar
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Gandhinagar
Regional Office
6-GJC040/2021-BHO
24/01/2022
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/GJ/TRANS/41280/2019
TRANS412802019350
66,078,712.00
66,078,712.00
2022-04-06
SBIN409576823858
Union Bank Of India
NEFT/RTGS (Challan)
2022-03-30
2022-03-30
19.
Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details) :
No
20.
Mutation Details Verified By Nodal Officer
Proposal No.
Verified Date
Mutation Letter
Remarks
FP/GJ/TRANS/41280/2019
16 Apr 2022
No Data
0k
21.
Compliance Details Submitted by User Agency
Proposal No.
Compliance Details submitted on(Date)
Uploaded Letter
FP/GJ/TRANS/41280/2019
26 Sep 2024
Compliance Details Submitted by User Agency(old)
Proposal No.
Compliance Details submitted on(Date)
Reject Remarks
Reject Date
Uploaded Letter
FP/GJ/TRANS/41280/2019
01 Jul 2024
EDS: as per GOI query
01 Aug 2024
FP/GJ/TRANS/41280/2019
16 Apr 2022
EDS: please submitte FRA certificate.
25 Apr 2024
22.
Compliance Details Verified by Nodal Officer
Proposal No.
Remarks
Verified Date
Uploaded Letter
FP/GJ/TRANS/41280/2019
As per the letter
02 Jul 2022
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/GJ/TRANS/41280/2019
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×