PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
GJ-0375/2021
1.
Location of the project/Scheme :
Gujarat
(i)
State / Union Territory :
Gujarat
(ii)
District :
Sabar Kantha
(iii)
Forest Division :
Sabarkantha
 (iv)
Area of forest land proposed for diversion (in ha.) :
0.1305
 (v)
Category of the Proposal:
Optical Fibre Cable
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Sabarkantha
0.1305
Reserved Forest
Total
0.1305
Division 1. : Sabarkantha
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Sabar Kantha
0.1305
Total
0.1305
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
0.1305
0.4
Eco 3
Total.
0.1305
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
NIL
5.
Working plan prescription for the forest land proposed for diversion :
NIL
6.
Brief note on vulnerability of the forest area to erosion :
Chancer of Soil erosion by wind and roin drop
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0.0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
Bear, Leopard & Python
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
No
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
No
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i).
Total Financial Outlay for C.A(lacs):
Patch Wise Details
S.no
Patch No.
Area(ha.)
Name of PF/RF
Range
Compartment No
Uploaded KML file of patch
NO Data
(ii).
Copy of CA scheme details:
NA
(iii).
Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iv).
Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
(V).
Copy of NOC from Competent Authority:
Additional information Details
S. No.
Documents
Remarks
1
In-Principal
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Sabar Kantha
4105.80
815.03
208.98.98
46
163.0104
07/12/2021
163.0104
0
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Sabarkantha
Gandhinagar Circle
DFO
Yes
One
07/12/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Sabarkantha
Gandhinagar Circle
DFO
Recommended
The telecom cables are always laid along the road side due to easy supervision, quick maintenance and low cost of maintenace The Applicant does not have to acquire land for this purpose as the road side land belongs to PWD gujrat state laying of cable shall be done on a 45 cm. width of surface land, & up to 1.65 meter of depth and near to the extreme road boundary where alignment of trench will be done in such way that no tree will be required to be cut. The laying of telecom transmission cable along roadside is an agreed policy of the Applicant and Ministry Surface Transport.
Gandhinagar Circle
CF
Recommended
Yes, Recommended
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Gujarat
State Secretary
Recommended
10/02/2022
Inprinciple Stage 1 approval will be issued by DCF
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Gandhinagar
State Government
C/FCA/T-14/781-85/21-22
17/01/2022
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/GJ/OFC/147320/2021
IN-PRINCIPLE
No Data
Print
Checklist for State Nodal Officer
×