PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : CG-06/2021
1. Location of the project/Scheme : Chhattisgarh
 (i) State / Union Territory : Chhattisgarh  (ii) District : Gariaband,Dhamtari  (iii) Forest Division : Udanti Sitanadi Tiger Reserve Gariyaband  (iv) Area of forest land proposed for diversion (in ha.) : 8.965  (v)

Category of the Proposal: Optical Fibre Cable
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Udanti Sitanadi Tiger Reserve Gariyaband4.193Reserved Forest
2Udanti Sitanadi Tiger Reserve Gariyaband4.772Protected Forest
Total 8.965
Division 1. : Udanti Sitanadi Tiger Reserve Gariyaband
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Gariaband6.967
2Dhamtari1.998
Total8.965
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
18.9650.6Eco 3
Total. 8.965


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Arjunarjun000000
Total 0 00 00 0
Sub Total (No of Trees.) 0


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : The OFC line laying in Right of way of existing road so that no any possibility of erosion in forest area
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : NA
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : The proposed OFC Cable laying within Right of Way of existing road so that There is no any measurable impact on wildlife
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : The OFC line laying in Right of way of existing road by using HDD or manual trenching practice so that no any measurable impact on applied area
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1KankerPondgaon8.965174
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
1 Bharat Net Project Approval
2 Recommendation Latter
3 FRA NOC
4 dgps suervey report
5 Wildlife Meeting MInuts
6 Area Details
7 64H12 FC map
8 64L03 FC map
9 64L04 FC map
10 64L12 FC map
11 65I05 FC map
12 65I09 FC map
13 Route passing map
14 Topo Sheet SOI-1
15 Topo Sheet SOI-2
16 Site inspection report
17 64H16 FC map
18 64L07 FC map
19 64L08 FC map
20 65I01 FC map
21 DD new
22 Deputy Director Recommendation (PART-II)
23 SITE INSPCETION REPORT (PRAPTRA-3)
24 Gariyaband CA Proposal
25 DGPS Report Pondgaon Antagarh

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Gariaband582286.00379440.0019.4404015/11/202100
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
Udanti Sitanadi Tiger Reserve GariyabandUdanti Sitanadi Tiger Reserve RaipurDFOYesOne29/10/2021
 Udanti Sitanadi Tiger Reserve RaipurCFNoNo Data
 Nodal OfficerNoNo Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
Udanti Sitanadi Tiger Reserve GariyabandUdanti Sitanadi Tiger Reserve RaipurDFO RecommendedUnder this project, connectivity will be provided at GramPanchayats & Blocks through optical fibre cable laying within existing ROW of Arsikanhar, Indagoan, Risgaon, Sitanadi, South Undati, North Undati, Tourenga, Kulhadighat Ranges with in Udanti Sitanadi Tiger Reserve Gariyaband Forest Division in Area 8.965 ha. Proposal Recommended
Udanti Sitanadi Tiger Reserve RaipurCF RecommendedThe proposed OFC Cable laying within Right of Way of existing road so that There is no any measurable impact on wildlifeYes
Nodal Officer RecommendedEnclosed
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
ChhattisgarhState SecretaryRecommended21/12/2023In Principle ApprovalState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
RaipurState GovernmentF 5-27/2023/10-219/12/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/CG/OFC/45530/2020OFC45530202048069,498,614.0069,498,600.002024-01-16INDBR32024011600674796Union Bank Of IndiaNEFT/RTGS (Challan)2024-01-112024-01-12
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 8.965   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)8.965
  Status of CA Land so identified : Forest Area   Site Name : Antagarh Forest Range, East Bhanupratappur Forest Division   Location Details : Khasra No. 174, Village - Pondgaon, Tehsil - Antagarh, Dist. - Kanker   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Revenue Forest AreaOther Forest Land
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/CG/OFC/45530/202030 Jan 2024No DataVerify
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/CG/OFC/45530/202002 May 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/CG/OFC/45530/202013 May 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/CG/OFC/45530/2020IN-PRINCIPLENo Data