PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : AS-08/2016
1. Location of the project/Scheme : Assam
 (i) State / Union Territory : Assam  (ii) District : Kokrajhar,Kajalgaon,Manikpur  (iii) Forest Division : Haltugaon,Chirang,Kachugaon  (iv) Area of forest land proposed for diversion (in ha.) : 208.807  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Kachugaon 4.136Reserved Forest
2Chirang 134.588Reserved Forest
3Haltugaon70.083Reserved Forest
Total 208.807
Division 1. : Chirang
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Kajalgaon,Manikpur134.588
Total134.588
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
1104.87135Eco 1
229.71735Eco 1
Total. 134.588


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersACRENUT 0270000
2Ficus RacemosaADUMRA 0609312
3Emblica SpsAMLA064521
4OthersAMTUS020000
5OthersASOOL010000
6OthersBADANGI070010
7OthersBAGNANA07118935
8Zizyphus JujubaBAIR0239200
9OthersBAIRUL000002
10Terminalia BellaricaBAWRA076411
11OthersBHANDERGIRI004302
12OthersBANDERGIRI004302
13OthersBHOLA 018458201824
14OthersBHOLAM053119911363185
15OthersDAWA032012
16OthersDAWALI05619743
17Lagerstroemia ParvifloraDOKRI01081035
18OthersDONGPONG070001
19Abies AlbaEMLI001010
20OthersFADONG001220
21Gmelina ArboreaGAMHARI07535222021
22Melia AzadirachtaGHORA NEEM020000
23OthersJAMUN0309437
24OthersJIYABAM03312547
25Nalla MaddiKADAM 020101
26OthersKAMLA020000
27Artocarpus HeterophyllusKATHAL011112
28OthersKHARUKHANDAI0145111
29OthersKHAWALA020000
30OthersKONDAI020000
31OthersKUM02961356
32OthersLAIDOLT0206213
33OthersLALIJIYA029157721
34OthersLEMON060000
35OthersLOKARI0566954912
36OthersMADLA071110
37OthersMAINA032200
38Calatropis giganteaMODAR023131321
39Mangifera IndicaAAM042112
40OthersMUGASONG0148543
41OthersODAL0211514127
42Lagerstroemia ParvifloraOJHAR061223
43OthersOXI0457140634838
44OthersPADAM030101
45OthersSHATUT020000
46OthersSERPANG0202110835
47Shorea RobustaSAL066211
48Bombax CeibaSIMOLU07128957
49Tectona GrandisTEAK09518200
50OthersSINDUR065020
51OthersSTONA034614
52Cinnamomum ZeylanicumTEJPATA040101
53OthersTHAILATOP02315900
54OthersUMAMEKHLA03010203
Total 0 2032773 433242 472
Sub Total (No of Trees.) 3952


5. Working plan prescription for the forest land proposed for diversion : WORKING PLAN UNDER WESTERN ASSAM CIRCLE (WAC) KOKRAJHAR IS UNDER PROGRESS.
6. Brief note on vulnerability of the forest area to erosion : NOT VULNERABLE TO EROSION. MOST OF THE TRANSMISSION LINE ROUTE IS PASSING THROUGH FOREST VILLAGES EXCEPT FROM LOCATION AP 4 TO LOC AP 5
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 2
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : MOST OF THE FOREST LAND PROPOSED FOR DIVERSION IS COVERED BY FOREST VILLAGES. WILDLIFE PRESENT IN AND AROUND THE PROPOSED FOREST LAND ARE MAINLY ELEPHANT AND OTHER COMMON WILD ANIMALS LIKE FOX AND SPECIES FROM CIVET FAMILIES.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : SINCE MOST OF THE FOREST LAND PROPOSED FOR DIVERSION IS COVERED BY FOREST VILLAGES IMPACT ON WILD ANIMALS WILL BE MINIMAL. HOWEVER, BETWEEN TOWER LOCATION AP-4 AND LOCATION AP-5, THERE EXISTS ELEPHANT HABITAT FOR WHICH SPECIAL PROTECTION MEASURES ARE REQUIRED LIKE INCREASE OF TOWER HEIGHT ETC. ALL PRECAUTIONARY MEASURES IN WILDLIFE ELEPHANT CORRIDOR IS REQUIRED TO BE ADHERED BY THE USER AGENCY AS PER MoEF GUIDELINE FOR TRANSMISSION LINES PASSING THROUGH WILDLIFE CORRIDOR DTD. 19TH NOV, 2014.
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : AN ELEPHANT HABITAT IS LOCATED WITHIN 1 KM OF THE PROPOSED FOREST AREA. HOWEVER, SINCE MOST OF THE FOREST LAND PROPOSED FOR DIVERSION IN CHIRANG FOREST DIVISION IS COVERED BY FOREST VILLAGES, IMPACT ON WILD ANIMALS WILL BE MINIMAL. BETWEEN TOWER LOCATION AP4 AND LOCATION AP5, THERE EXISTS ELEPHANT HABITAT AND CORRIDOR FOR WHICH SPECIAL PROTECTION MEASURES ARE REQUIRED LIKE INCREASE OF TOWER HEIGHT ETC. ALL PRECAUTIONARY MEASURES IN WILDLIFE HABITAT ELEPHANT CORRIDOR IS REQUIRED AS PER
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 130.613324
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1171PHULKUMARI RF Khoraghar 3    View file
2245BHELAKOPA R F Khoraghar 7    View file
33154MAHAMAYA R F Khoraghar 25    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 CA AREA INSPECTION PHOTOS OF PARBATJHORA DIVISION
2 COMPLIANCE LETTER OF DFO, CHIRANG AGAINST NODAL OFFICE OBSERVATION
3 ESTIMATE FOR DWARF SPP. PLANTATION SCHEME, CHIRANG DIVISION
4 ABSTRACT OF CA, NPV CHIRANG FOREST DIVISION
5 SITE INSPECTION REPORT OF DFO, CHIRANG DIVISION WITH PHOTOGRAPHS FOR THE FOREST LAND PROPOSED FOR DIVERSION BY POWERGRID
6 DFO's letter regarding availability of land for CA in Parbotjhora Division
7 CF letter regarding availability of CA area
Division 2. : Haltugaon
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Kokrajhar70.083
Total70.083
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
15.40930Eco 1
264.67430Eco 1
Total. 70.083


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersAckee010011
2OthersAcrea Nut040000
3Ficus RacemosaUdumbara04515100
4Emblica SpsAmla001000
5Lagerstroemia ParvifloraOjhar01710721
6Terminalia BellaricaBawra074312
7OthersCoconut010000
8Gmelina ArboreaGamhari01213717150
9Psidium GuajavaGowava020000
10OthersHaldiya010000
11Syzigium CuminiJamun050000
12OthersJiyabum0155001
13OthersJumra050000
14OthersKadam013000
15OthersKantakuri030000
16Artocarpus HeterophyllusKothal042617
17OthersKesar045301
18OthersKharukhandai0113100
19OthersKonger Thisip010000
20OthersKum030000
21OthersLafasaiko010000
22OthersLaidlot06412000
23OthersLalijiya0120410
24OthersLeyorko011000
25OthersLokari011001
26Calatropis giganteaMandar010000
27Mangifera IndicaMango082324
28OthersMogasong0305300
29Melia AzadirachtaNeem02410110
30OthersOdal055120
31OthersPapita010000
32OthersSehtuth060000
33OthersSerphang060001
34SalShal041000
35OthersShindoor020000
36OthersShumli08129410
37Tectona GrandisSigun060000
38Dalburgia SisooSisu000011
39OthersStona011011
40OthersSujray010000
41OthersSweet Lime092000
42OthersThaigir022300
43OthersThailatop0192100
44OthersTitasap030200
45OthersUmamekla0131100
46OthersZumra002000
Total 0 479144 6632 31
Sub Total (No of Trees.) 752


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : Non vulnerable to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 1.0
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Wild Elephant and other wild species of civet families.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : The Forest Land proposed for diversion falls under Chirang RF, which is a part of greater CHIRANG-RIPU ELEPHANT RESERVE. However most of the proposed Transmission Line Route is passing through Forest Villages, however the area is sometimes frequented by wild elephant.
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : The Forest Land proposed for diversion falls under Chirang RF, which is a part of greater CHIRANG-RIPU ELEPHANT RESERVE. However most of the proposed Transmission Line Route is passing through Forest Villages, however the area is sometimes frequented by wild elephant.
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 659.39497
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
11141CHIRANGUltapani 4    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 ESTIMATE FOR DWARF SPP. PLANTATION SCHEME, HALTUGAON DIVISION
2 COMPLIANCE LETTER OF DFO, HALTUGAON AGAINST NODAL OFFICE OBSERVATION
3 ABSTRACT OF CA, NPV HALTUGAON DIVISION
4 CALCULATION OF NPV, HALTUGAON DIV
5 ALTERNATE CA AREA PHOTOS OF PARBATJHORA DIVISION
6 PHOTOGRAPHS OF SITE INSPECTION FOR THE PROPOSED LAND DIVERSION OF 70.083HA FOREST LAND ALONG WITH COMPENSATORY AFFORESTATION PLANTATION AREA BY HALTUGAON FOREST DIVISION & POWERGRID STAFF
7 SITE INSPECTION REPORT OF DFO, HALTUGAON DIVISION
Division 3. : Kachugaon
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Kokrajhar4.136
Total4.136
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
14.13630Eco 1
Total. 4.136


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Ficus RacemosaAdumra011000
2Dalburgia SisooSisoo038230
3Bombax CeibaSimul000001
4OthersSEWRA020000
5OthersTHALIATOP010000
6OthersUMAMEKHLA010000
7OthersLOKARI001020
Total 0 810 25 1
Sub Total (No of Trees.) 26


5. Working plan prescription for the forest land proposed for diversion : Present working plan under Western Assam Circle, Kokrajhar is under process.
6. Brief note on vulnerability of the forest area to erosion : Non-vulnerable to erosion
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : .3
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Since the proposed area is open, no wild life is found in that area.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : No
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : No
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 91.58546
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
118.5GumaGuma 3    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
1 SITE INSPECTION REPORT OF DFO, KACHUGAON DIVISION WITH PHOTOGRAPHS FOR THE FOREST LAND PROPOSED FOR DIVERSION BY POWERGRID
2 ESTIMATE FOR DWARF SPP. PLANTATION SCHEME, KACHUGAON DIVISION
3 COMPLIANCE LETTER OF DFO, KACHUGAON AGAINST NODAL OFFICE OBSERVATION
4 ABSTRACT OF CA, NPV KACHUGAON DIVISION
5 DFO's letter regarding availability of CA land in Parbatjhora Division
6 CF letter for availability of CA land

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Kokrajhar3169001107005.068215031/03/20161500
2Kajalgaon,Manikpur14680096491.611031/12/201600
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
HaltugaonWestern Assam Circle, KokrajharDFOYesThree02/09/2016,08/09/2016,20/09/2016
ChirangWestern Assam Circle, KokrajharDFOYesOne05/01/2017
KachugaonWestern Assam Circle, KokrajharDFOYesOne23/11/2016
 Western Assam Circle, KokrajharCFYesOne29/01/2017
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
HaltugaonWestern Assam Circle, KokrajharDFO Recommended
ChirangWestern Assam Circle, KokrajharDFO RecommendedTHE CONSTRUCTION OF THE TRANSMISSION LINE IS A GOVT. OF INDIA PROJECT HAVING NATIONAL INTEREST. IT WILL IMPROVE THE OVERALL POWER SCENARIO WITHOUT WITHOUT MAJOR DAMAGE OF FOREST AND ENVIRONMENT PROVIDED MITIGATIVE MEASURES ARE IMPLEMENTED BY USER AGENCY AS PER GUIDELINE. THEREFORE THE DIVERSION OF THE ABOVE FOREST LAND IS RECOMMENDED FOR APPROVAL.
quetiapin ritalin markenavntablet.site quetiapin wirkstoff
KachugaonWestern Assam Circle, KokrajharDFO RecommendedTHE CONSTRUCTION OF THE TRANSMISSION LINE IS A GOVT. OF INDIA PROJECT HAVING NATIONAL INTEREST. IT WILL IMPROVE THE OVERALL POWER SCENARIO WITHOUT WITHOUT MAJOR DAMAGE OF FOREST AND ENVIRONMENT. THEREFORE THE DIVERSION OF THE SUBJECT FOREST LAND IS RECOMMENDED FOR APPROVAL.
Western Assam Circle, KokrajharCF RecommendedThe construction of the Transmission line is a Govt. of India project having National interest. It will improve the overall power scenario without major damage of forest and environment provided mitigation measures are implemented by User Agency as envisaged in the report of concerned DFOs and as per MoEF guideline. Therefore, the diversion of the forest land as above is recommended for acceptance. Yes
Nodal Officer RecommendedRecommended
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
AssamState SecretaryRecommended13/05/2017Recommended owing to national importance of the prState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
GuwahatiRegional Office3-AS C 023/2017-SHI18/10/2018
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/AS/TRANS/19330/2016TRANS193302016842472,029,867.00472,029,867.0005/12/2018SBINR12018120500008087Corporation BankNEFT/RTGS (Challan)01/12/201801/12/2018
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 419.5   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 5
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)71
  Status of CA Land so identified : Forest Area   Site Name : PHULKUMARI RF   Location Details : KHORAGHAR   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
PHULKUMARI RFRF
  No. of patches : 2
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
2Block(Polygon)45
  Status of CA Land so identified : Forest Area   Site Name : BHELAKOPA RF   Location Details : KHORAGHAR RANGE   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
BHELAKOPA RFRF
  No. of patches : 3
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
3Block(Polygon)154
  Status of CA Land so identified : Forest Area   Site Name : MAHAMAYA RF   Location Details : KHORAGHAR RANGE   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
MAHAMAYA RFRF
  No. of patches : 4
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
4Block(Polygon)141
  Status of CA Land so identified : Forest Area   Site Name : CHIRANG RF   Location Details : ULTAPANI RANGE   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
CHIRANG RFRF
  No. of patches : 5
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
5Block(Polygon)8.5
  Status of CA Land so identified : Forest Area   Site Name : GUMA RF   Location Details : GUMA RANGE   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
GUMA RFRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/AS/TRANS/19330/201602 Jan 2021No DataThe uploaded CA details are verified and found to be correct.
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/AS/TRANS/19330/201602 Jan 2021
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/AS/TRANS/19330/201608 Jan 2021
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/AS/TRANS/19330/201615 Feb 2021APPROVED