PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : AS-057/2021
1. Location of the project/Scheme : Assam
 (i) State / Union Territory : Assam  (ii) District : Cachar  (iii) Forest Division : Cachar  (iv) Area of forest land proposed for diversion (in ha.) : 9.23  (v)

Category of the Proposal: Transmission Line
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Cachar 9.23Protected Forest
Total 9.23
Division 1. : Cachar
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Cachar9.23
Total9.23
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
19.230.6Eco 1
Total. 9.23


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1Duabanga GrandifloraRamdala0062000
2Terminalia bellericaBoera017700
3Chukrasia TabularisPoma000500
4Gmelina AroboreaGamari004000
5OthersTula0014200
6OthersJam01132100
7OthersRata050800
8OthersD. Cham001500
9OthersPing001400
10OthersBonak002600
11OthersAwal003300
12OthersBolos001600
13OthersUdal023300
14OthersFuara016400
15OthersBadam002500
16OthersMisc01511000
Total 0 3551 1390 0
Sub Total (No of Trees.) 225


5. Working plan prescription for the forest land proposed for diversion : NIL
6. Brief note on vulnerability of the forest area to erosion : No
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 0.15
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : Slow loris, Rhesus Macaque, Pig tailed Macaque, Stump-tailed Macaque, Assamese Macaque, Capped langur, Phayre's Leaf Monkey, Hollock Gibbon, Sloth Bear, Malayan Sun Bear, Fruit Bat, Clouded Leopard, Field mouse, Wood ra, Jungle cat, Pangolin, Bamboo rat, Pipstrelle, Hog deer, Barking deer, Goral, Porcupine, Jeckal, Wild Boar, Assam roofed turtle, River Terrapin, Box urtle, Pond turtle, River turtle, Softshell turtle, Indian Phython, Viper, Green kul back, Ra Snake, Checkered kuel back, Cobra, Common Krait, Monitor lizard, King cobra
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : As the project is meant for transmission line, hence impact upon the area is negligible
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): Yes
  Details of Protected Area and comments on the impact of Project on the ESZ : As the project is meant for transmission line, hence impact upon the area is negligible
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : As the project is meant for transmission line, hence impact upon the area is negligible
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : No
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
Patch wise details for Degraded Area (To be earmarked by DFO)
(i). Total Financial Outlay for C.A(lacs): 52.48843
Patch Wise Details
S.no Patch No.Area(ha.)Name of PF/RFRangeCompartment NoUploaded KML file of patch
1120Lower JiriJirighat 83 H/1    View file
(ii). Copy of CA scheme details: (iii). Scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iv). Copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A.:
 (V). Copy of NOC from Competent Authority :

Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Cachar37750086284.54150.2915260.52817/12/2021260.52821.25
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
CacharC.F Southern Assam Circle, SilcharDFOYesThree16/09/2021,10/10/2021,10/11/2021
 C.F Southern Assam Circle, SilcharCFYesOne31/12/2021
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
CacharC.F Southern Assam Circle, SilcharDFO RecommendedThe construction of the transmission line is a Govt. of India Project having national interest, as relocation of the said transmission line is required to successfully execute the Balacherra Harangajao 4 lane Highway
C.F Southern Assam Circle, SilcharCF Recommended? The diversion work of 132 KV S/C Haflong Jiribam Transmission line of Power Grid Corporation under Borail Wildlife Sanctuary East Block under Cachar Division is needed for facilitating to execute the construction of Balacherra Harengajao 4 lane Highway a Govt. of India Project having National interest. It will improve the communication system of the North Eastern region without causing major damage of the forest and environment provided mitigated measures are implemented by the User Agency as per guideline of F.C.Act,1980. As the forest area proposed for diversion is unavoidable and barest minimum required for the project, therefore, the diversion of the forest land as above is recommended for acceptance subject to fulfillment of the terms and conditions of F.C.Act . Yes
Nodal Officer RecommendedAs the forest area proposed for diversion is unavoidable and barest minimum required for the project, therefore, the diversion of the forest land as above is recommended for acceptance subject to fulfillment of the terms and conditions of F.C.Act .
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
AssamState SecretaryRecommended20/04/2022RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
GuwahatiRegional Office3-AS-C-096/2022/GHY09/02/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/AS/TRANS/119559/2021TRANS119559202179087,073,341.0087,073,341.002023-04-03918021Union Bank Of IndiaNEFT/RTGS (Challan)2023-03-242023-03-24
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 20   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)20
  Status of CA Land so identified : Forest Area   Site Name : Lower Jiri Reserve Forest   Location Details : NIL   Uploaded GPS File :   Uploaded Scanned copy of Map :
Status of CA Land so identified
Name of Forest. Legal Status of Forest Land
Lower Jiri Reserve ForestRF
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/AS/TRANS/119559/202111 Apr 2023No DataVerified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/AS/TRANS/119559/202111 Apr 2023
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/AS/TRANS/119559/2021Approved In-PrincipleNo Data