PART-II
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal : AS-032/2022
1. Location of the project/Scheme : Assam
 (i) State / Union Territory : Assam  (ii) District : Tinsukia  (iii) Forest Division : Digboi  (iv) Area of forest land proposed for diversion (in ha.) : 3.92  (v)

Category of the Proposal: Mining
2. Legal status of forest land proposed for diversion
S. No. DivisionForest Land(ha.)Legal Status
1Digboi3.92Reserved Forest
Total 3.92
Division 1. : Digboi
3. District wise area to be diverted in the division
S. No. DistrictArea(ha.)
1Tinsukia3.92
Total3.92
4. Details of Vegetation available in the forest land proposed for diversion
 (i) Density of vegetation
S. No. Area(in ha.)Density Eco-Class
10.80.5Eco 1
20.80.3Eco 1
32.320.3Eco 1
Total. 3.92


(ii) Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No. Scientific Name Local Name (0-30)cm. (31-60)cm. (61-90)cm. (91-120)cm. (121-150)cm. (>150)cm.
1OthersHengalu04141423
2OthersGumati001100
3OthersGohora001000
4OthersHatipoila000010
5OthersSotiana001011
6OthersUriam002004
7OthersKoram011000
8OthersParoli001102
9OthersBontezpat002000
10OthersGomari000014
11OthersBarhamthuri001201
12OthersHallakh000100
13OthersKaka bamboo5000000
14OthersJamuk010000
15OthersBowal001100
16OthersBonsum010000
Total 50 725 205 15
Sub Total (No of Trees.) 122


5. Working plan prescription for the forest land proposed for diversion : Plantation working circle under draft working plan
6. Brief note on vulnerability of the forest area to erosion : As no rivers or major streams traverse the area, the area is not vulnerable to erosion.
7. Approximate distance of the proposed site for diversion from boundary of forest(in km.) : 1.75
8. Significance of the forest land proposed for diversion from wildlife point of view
 (i). Details of wildlife present in and around the forest land proposed for diversion : The area has various species including elephants, leopard, hoolock gibbon etc.
 (ii). Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. : Yes
  Details and comments on the impact of Project on such areas : The proposed area is part of Dehing Patkai Elephant Reserve. Use of heavy machinery could also have adverse impact on animals living in the area, especially during drilling and workover operations. Also, this could increase the man animal conflict in adjoining areas. A biodiversity and man animal conflict management plan is to be prepared to accurately assess and address the issues that could arise.
 (iii). Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ): No
 (iv). Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion : Yes
  Details and comments on the impact of Project on such areas : The proposed area is part of Dehing Patkai Elephant Reserve. Use of heavy machinery could also have adverse impact on animals living in the area, especially during drilling and workover operations. Also, this could increase the man animal conflict in adjoining areas. A biodiversity and man animal conflict management plan is to be prepared to accurately assess and address the issues that could arise.
 (v). Whether any rare/endangered/unique species of flora and fauna found in the area : Yes
9. Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
 (i). Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area : No
10. Comment as to the reasonability of the extent of the forest land proposed for diversion
 (i). Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project : Yes
11. Details of violation(s), if any ,committed
 (i). Whether any work in violation of the Act or guidelines issued under the Act has been carried out : No
12. Whether work in violation is still in progres(Yes/No) : NIL
13. Details of compensatory afforestation scheme
(i). Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no District Name VillageArea(in ha.)khasraKML filePresent Owner file
1HaflongLungdingkro3.92N/A
(ii). Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station: (iii). Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A: (iv). Copy of CA scheme details: (iv). Copy of CA scheme details: NA
Additional information Details
S. No. DocumentsRemarks
NIL

14. District Profile
S.no District NameGeographical area of the district (in ha.)Forest area of the district (in ha.)Total forest area diverted since 1980 (in ha.)No. of Approved CasesForest Land including penal C.A. (in ha.)Progress of compensatory afforestation as on(date)A) Forest land (in ha.)B) Non-forest land (in ha.)
1Tinsukia379000158257164.895633028/04/20223300
15. Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division NameCircleSite inspected ByWhether site inspectedNo. of times site visited Site inspection reportDate of visit
DigboiC.F. E.A.C, JorhatDFOYesOne10/05/2022
 C.F. E.A.C, JorhatCFYesOne23/05/2022
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16. Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
DivisionCircleRecommendation ByRecommendationReasonLetter Whether CF agreed
DigboiC.F. E.A.C, JorhatDFO RecommendedThe proposed area has thin vegetation as it was previously drilled and the road is also present and is used by forest department. Considering the above and considering the need of energy , the proposal as received is recommended provided the conditions given in recommendation report is fulfilled .
C.F. E.A.C, JorhatCF RecommendedSpecific recommendation is attached. Yes
Nodal Officer RecommendedAs per DFO, Digboi, the proposed area has thin vegetation as it was previously drilled and the road is also present and is used by forest department. Considering the above and considering the need of energy , the proposal is hereby recommended.
Specific recommendation of the State Government(Part V)
17. Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
StateRecommendation ByRecommendationRecommendation DateRemarksSigning AuthorityNotificationRecommendation Letter
AssamState SecretaryRecommended12/07/2022RecommendedState Govt. OfficerNo Data
17. Stage-I Clearance Report
Regional OfficeRecommendation ByMoEF File No.Date of Stage-I ClearanceClearance Letter
GuwahatiRegional Office3-AS-B-114/2022/GHY29/08/2023
18. Payment made by User Agency
Proposal No.Application No.Total Amount (Rs.)Recieved Amount (Rs.)Transaction DateTransaction IDBank NameMode of PaymentDemmand Generated By User AgencyDemmand Verified By Nodal OfficerUploaded Demand Letter
FP/AS/MIN/154403/2022MIN154403202271836,542,657.0036,542,700.0004/12/2023HDFCR52023120559443815Union Bank Of IndiaNEFT/RTGS (Challan)NANA
FP/AS/MIN/154403/2022MIN15440320223796,000,000.006,000,000.0021/12/2023HDFCR52023122164203062Union Bank Of IndiaNEFT/RTGS (Challan)06/12/202308/12/2023
19. Uploaded Status of Land to be transferred to Forest Department under FCA (Mutation Details).
  (i). Whether CA Land is mandatorily required in this Proposal : Yes   (ii). Total Land identified for raising CA: 9.3   (iii). No. of Maintenance years: 10   (iv). Total No. of Patches/Parcel: 1
  No. of patches : 1
Patch wise details
Patch No. Shape of land identified for CA Area of Patch/Parcel(in ha.)
1Block(Polygon)3.92
  Status of CA Land so identified : Non Forest Area   Site Name : Lundingkro village under Langting lot   Location Details : Lundingkro village under Langting lot   Uploaded GPS File :   Uploaded Scanned copy of Map :   Mutation Status : Mutated
Mutation Status
Circle Name. Name of Division. Name of Range. Mutation Order No. Mutation Date How Much Area of Mutated Land Received Mutation Letter
Dima Hasao Circle(council) HaflongDima Hasao Forest East Division, HaflongLangtingREV/S/85/OIL/2021-22/08 Dec 20233.92
20. Mutation Details Verified By Nodal Officer
Proposal No.Verified DateMutation LetterRemarks
FP/AS/MIN/154403/202211 Jan 2024No DataVerified
21. Compliance Details Submitted by User Agency
Proposal No.Compliance Details submitted on(Date)Uploaded Letter
FP/AS/MIN/154403/202212 Jan 2024
22. Compliance Details Verified by Nodal Officer
Proposal No.RemarksVerified DateUploaded Letter
FP/AS/MIN/154403/202213 Jun 2024
23. Stage-II Clearance Details
Proposal No.Date of Stage-II ClearanceProposal StatusClearance Letter
FP/AS/MIN/154403/202224 Dec 2024APPROVED